Compensation Event and Quotation
|
|
1
|
225
|
7 May 2024
|
Option E Programmes
|
|
3
|
328
|
7 May 2024
|
NEC4 ECC Clause 60.1 (8) in association with clause 61.4
|
|
2
|
654
|
30 April 2024
|
Release Notes upto 2024-04-30 Academy
|
|
0
|
180
|
30 April 2024
|
Release Notes up to 2024-04-27 Contract Management Sprint 88
|
|
0
|
142
|
29 April 2024
|
'Smash and grab' payment applications ad infinitum
|
|
1
|
293
|
28 April 2024
|
Planned Completion & Completion Date
|
|
1
|
213
|
28 April 2024
|
NEC4 Accepted Programme
|
|
1
|
195
|
28 April 2024
|
Query on add and delete referencing a tender rate
|
|
1
|
180
|
26 April 2024
|
NEC Option A Compensation Events with drawing revisions- How is Fee applied
|
|
1
|
180
|
26 April 2024
|
NEC4. Limitation of delay damages under X7
|
|
5
|
489
|
25 April 2024
|
PSC4 - People or Subcontractor
|
|
1
|
219
|
25 April 2024
|
People Rates for Specialist Sub-contractor
|
|
0
|
144
|
23 April 2024
|
NEC4 Subcontract Option A - Activity Schedule Clause 55
|
|
7
|
698
|
23 April 2024
|
Contract Programme - Access Dates
|
|
0
|
166
|
23 April 2024
|
Provisional items under NEC Type A contract
|
|
3
|
520
|
23 April 2024
|
NEC ECC: Disallowed cost of Defects due to failure by Contractor to Comply with Specification
|
|
8
|
3606
|
23 April 2024
|
Issue of GC to add an additional scope against existing scope of an EI
|
|
2
|
512
|
23 April 2024
|
What happened to this forum?
|
|
3
|
372
|
19 April 2024
|
30.2 Project Manager deciding Completion
|
|
1
|
623
|
18 April 2024
|
Cl 93.2 - The amount due on termination
|
|
2
|
200
|
16 April 2024
|
Release Notes up to 2024-04-13 Contract Management Sprint 86/87
|
|
0
|
136
|
15 April 2024
|
Release Notes up to 2024-03-02 Contract Management Sprint 84
|
|
0
|
235
|
18 March 2024
|
Release Notes up to 2024-03-17 Contract Management Sprint 85
|
|
0
|
259
|
18 March 2024
|
Assessment of additional work in terms of Impact on the programme
|
|
1
|
501
|
15 April 2024
|
NEC3 - Cl.60.1.(8)
|
|
1
|
531
|
15 April 2024
|
JCT (ICD) 2016 Inconsistency of documents - Rectification Period
|
|
1
|
464
|
15 April 2024
|
NEC Option B 60.4
|
|
1
|
289
|
15 April 2024
|
Use of Indemnity to Principal Clauses in lieu of Insurance Policies in Joint Names
|
|
1
|
522
|
15 April 2024
|
PSC3 Option C - withholding payment
|
|
1
|
587
|
15 April 2024
|