NEC4. Limitation of delay damages under X7

Is there a limitation on the amount of delay damages under X7 and, if so, where do I find that in the contract?
I believe it is 10% but I cannot find any reference to that.

1 Like

There is no limit on liquidated damages under the NEC4 contracts

Thank you for confirming that Steven

Martin Jagger
Tel. +44 7709 181691

I’m assuming these could be limited under an amendment?

Best Regards

Stuart Hasler

Custodial Director

GAME Engineering Ltd

Camp Road

Witham St Hughs Business Park

Witham St Hughs

Lincoln

LN6 9TW

ENGLAND

Tel: +44 (0)1522 868021

Mob: +44 (0)7515 597865

Fax: +44 (0)1522 868027

shasler@game-engineering.com

www.game-security-engineering.com

Registered in England 1872121

(Mobile Account)

Thanks Stuart.

We don’t have an amendment.

Regards

Martin Jagger
Tel. +44 7709 181691

There is no limit on NEC unamended. A Z clause would be required to add a cap.

I personally think NEC unamended should have a cap as standard though, as in practice, most LD’s are capped at anywhere from between 5 to 20% of the contract value.