I was hoping that the reachback community would be able to help me with the theory of how to apply %’s on the example I have below.
Contract is NEC ECC Option A
Direct Fee is 9.5%
Subcontracted Fee is 9.5%
Working Area is “The site”
Data for Shorter Schedule of cost components (SCoCC) is:
People overheads 16%
Equipment Adjustment n/a
Design Overheads 15%
The Contractor has submitted a quote and within this quote there are:
- The contractors Defined cost in line with the SCoCC mainly:
- People cost.
- Materials cost.
- The subcontractors defined cost in line with the SCoCC mainly:
- People cost
- Design costs.
My question to the community is, which percentages apply to each area of the contractor’s quotation?
I’m sure I will have follow up questions but any help on the above will be greatly appreciated.
1 Like
Taking each component in turn:
People
-
Amount paid by Contractor for Contractor’s people + % people overheads = sub total for Contractor’s people
-
Amount paid by Subcontractor for Subcontractor’s people + % people overheads = sub total for Subcontractor’s people
Plant and Materials
- Payments for purchasing Plant and Materials = sub total for Plant and Materials
Design
- (Total hours worked by Subcontractor’s employees x hourly rates in Contract Data) + % design overheads = sub total for design
The direct and subcontracted fee percentages are then applied to the relevant components to arrive at a total, in your case as the fee percentages are the same it doesn’t matter but it would be important to apply it correctly if they were different.