NEC ECC: People cost justification within SCC audit?
|
|
1
|
206
|
19 November 2019
|
NEC ECC: Freelance project manager - Subcontract Fee or Direct Fee percentage?
|
|
1
|
276
|
13 November 2019
|
NEC ECC: Quotations under NEC3 ECC - for subcontracted elements
|
|
1
|
131
|
5 November 2019
|
NEC ECC: Under Option B, how is Defined Cost applied to a compensation event?
|
|
1
|
221
|
1 November 2019
|
NEC ECC: Option C - Expenses Disallowed
|
|
1
|
172
|
30 October 2019
|
NEC ECC: What exactly should be included within the fee?
|
|
1
|
189
|
29 October 2019
|
NEC ECC: People Defined Cost Rates
|
|
2
|
426
|
20 October 2019
|
NEC ECC: Option B - Defined Cost for CE Assessment
|
|
1
|
219
|
7 October 2019
|
NEC ECC: What is included in 'buying & leasing land' within schedule of cost components?
|
|
1
|
105
|
3 October 2019
|
NEC3 ECC: Option C - The meaning of "Directly Employed" under People in SOCC
|
|
3
|
159
|
23 September 2019
|
NEC ECS: Subcontract Working Area Differs from Head Contract
|
|
1
|
107
|
18 September 2019
|
NEC ECC: Normal Place of Work
|
|
1
|
189
|
3 September 2019
|
NEC PSC: Option E staff rates
|
|
2
|
1202
|
2 September 2019
|
NEC ECC: Can you be paid for working outside of the Working Areas?
|
|
1
|
395
|
4 July 2019
|
NEC ECC: Do Labour rates in the SSOCC include the direct fee?
|
|
3
|
338
|
3 May 2019
|
NEC ECC: (Option C) - In accordance with the SOCC would a 'taxable site based travel allowance' be classified as 13 (b) 'subsistence and lodging'?
|
|
1
|
265
|
6 March 2019
|
NEC ECC: Can you have different fee percentages for different costs
|
|
1
|
242
|
6 February 2019
|
NEC ECS: Deduction for breaks?
|
|
1
|
278
|
5 February 2019
|
NEC ECS: When does incidental works become non-incidental?
|
|
2
|
229
|
3 February 2019
|
NEC ECC: Option C - Disallowed Costs
|
|
1
|
422
|
16 January 2019
|
NEC ECC: WAO on Cost of People within a Subcontract
|
|
3
|
247
|
11 January 2019
|
NEC ECC: Under an Option C contract, does the defined cost of "Equipment" include costs associated with repair and maintenance?
|
|
1
|
371
|
10 January 2019
|
NECECC: Is the provision of a company car, including a fully expensed fuel card allowed under defined cost for an Option C?
|
|
3
|
653
|
18 December 2018
|
NEC ECC: Option A - People Overheads
|
|
1
|
433
|
23 November 2018
|
NEC ECC: SCC- Item 44
|
|
4
|
438
|
25 October 2018
|
NEC3 ECC : Should the Project Completion Bonus be paid as part of Defined Cost
|
|
2
|
186
|
10 October 2018
|
NEC ECS: Is travel time payable under option A?
|
|
1
|
269
|
25 September 2018
|
NEC ECC: Working Area Overhead Percentage and Agreed Subcontract Rates
|
|
1
|
1557
|
26 August 2018
|
NEC ECS: What is the definition of a Subsubcontractor under NEC3?
|
|
3
|
379
|
10 July 2018
|
NEC ECC: Option C - removal of items 12/13 of SCC
|
|
1
|
255
|
7 June 2018
|