NEC ECC: Under an option C contract, how would items that have been instructed by the Project Manager be covered in the defined cost?
|
|
1
|
682
|
16 June 2020
|
NEC3 Option C disallowed Subcontractor costs
|
|
1
|
794
|
12 May 2020
|
NEC ECC: Defined Cost - Furlough Top Up Payments
|
|
1
|
1031
|
23 April 2020
|
NEC ECC: Design Costs under the schedule of cost components
|
|
1
|
863
|
16 April 2020
|
NEC ECC: Severance cost for People incurred under SSCC (during Covid-19 period)
|
|
1
|
804
|
9 April 2020
|
NEC ECC: Is it correct to use 2019 CECA rates in lieu of 2011 CECA rates after the original completion date?
|
|
1
|
870
|
1 April 2020
|
NEC4 ECC: Option B: completion of data for sscc
|
|
2
|
894
|
28 February 2020
|
NEC ECS: Subcontractors category removed from schedule of cost components
|
|
1
|
610
|
17 February 2020
|
NEC ECC: For an Option A contract, when measuring a CE should you use the agreed Contract Data Part 2 labour rates?
|
|
1
|
1535
|
14 February 2020
|
NEC ECC: Is cost of fuel for machines on site recoverable within the SCC?
|
|
2
|
837
|
24 January 2020
|
NEC ECC: Audit of people costs as per the Option E SCC
|
|
4
|
2569
|
22 November 2019
|
NEC ECC: Is Working Area Overhead a Defined Cost?
|
|
1
|
889
|
21 November 2019
|
NEC ECC: People cost justification within SCC audit?
|
|
1
|
753
|
19 November 2019
|
NEC ECC: Freelance project manager - Subcontract Fee or Direct Fee percentage?
|
|
1
|
908
|
13 November 2019
|
NEC ECC: Quotations under NEC3 ECC - for subcontracted elements
|
|
1
|
568
|
5 November 2019
|
NEC ECC: Under Option B, how is Defined Cost applied to a compensation event?
|
|
1
|
647
|
1 November 2019
|
NEC ECC: Option C - Expenses Disallowed
|
|
1
|
607
|
30 October 2019
|
NEC ECC: What exactly should be included within the fee?
|
|
1
|
598
|
29 October 2019
|
NEC ECC: People Defined Cost Rates
|
|
2
|
2174
|
20 October 2019
|
NEC ECC: Option B - Defined Cost for CE Assessment
|
|
1
|
640
|
7 October 2019
|
NEC ECC: What is included in 'buying & leasing land' within schedule of cost components?
|
|
1
|
690
|
3 October 2019
|
NEC3 ECC: Option C - The meaning of "Directly Employed" under People in SOCC
|
|
3
|
517
|
23 September 2019
|
NEC ECS: Subcontract Working Area Differs from Head Contract
|
|
1
|
430
|
18 September 2019
|
NEC ECC: Normal Place of Work
|
|
1
|
732
|
3 September 2019
|
NEC PSC: Option E staff rates
|
|
2
|
1820
|
2 September 2019
|
NEC ECC: Can you be paid for working outside of the Working Areas?
|
|
1
|
1427
|
4 July 2019
|
NEC ECC: Do Labour rates in the SSOCC include the direct fee?
|
|
3
|
906
|
3 May 2019
|
NEC ECC: (Option C) - In accordance with the SOCC would a 'taxable site based travel allowance' be classified as 13 (b) 'subsistence and lodging'?
|
|
1
|
1021
|
6 March 2019
|
NEC ECC: Can you have different fee percentages for different costs
|
|
1
|
550
|
6 February 2019
|
NEC ECS: Deduction for breaks?
|
|
1
|
1152
|
5 February 2019
|