|
NEC ECC: How are Prices reviewed for a compensation event that is an instruction from the Employer?
|
|
1
|
637
|
26 June 2020
|
|
NEC ECC: Interpretation of NEC4 SOCC
|
|
1
|
2095
|
25 June 2020
|
|
NEC ECC: Same Subcontract fee percentage applied to subcontracts under option A and C?
|
|
2
|
1045
|
16 June 2020
|
|
NEC ECC: Under an option C contract, how would items that have been instructed by the Project Manager be covered in the defined cost?
|
|
1
|
720
|
16 June 2020
|
|
NEC3 Option C disallowed Subcontractor costs
|
|
1
|
862
|
12 May 2020
|
|
NEC ECC: Defined Cost - Furlough Top Up Payments
|
|
1
|
1044
|
23 April 2020
|
|
NEC ECC: Design Costs under the schedule of cost components
|
|
1
|
934
|
16 April 2020
|
|
NEC ECC: Severance cost for People incurred under SSCC (during Covid-19 period)
|
|
1
|
891
|
9 April 2020
|
|
NEC ECC: Is it correct to use 2019 CECA rates in lieu of 2011 CECA rates after the original completion date?
|
|
1
|
911
|
1 April 2020
|
|
NEC4 ECC: Option B: completion of data for sscc
|
|
2
|
934
|
28 February 2020
|
|
NEC ECS: Subcontractors category removed from schedule of cost components
|
|
1
|
630
|
17 February 2020
|
|
NEC ECC: For an Option A contract, when measuring a CE should you use the agreed Contract Data Part 2 labour rates?
|
|
1
|
1659
|
14 February 2020
|
|
NEC ECC: Is cost of fuel for machines on site recoverable within the SCC?
|
|
2
|
928
|
24 January 2020
|
|
NEC ECC: Audit of people costs as per the Option E SCC
|
|
4
|
2944
|
22 November 2019
|
|
NEC ECC: Is Working Area Overhead a Defined Cost?
|
|
1
|
1004
|
21 November 2019
|
|
NEC ECC: People cost justification within SCC audit?
|
|
1
|
825
|
19 November 2019
|
|
NEC ECC: Freelance project manager - Subcontract Fee or Direct Fee percentage?
|
|
1
|
977
|
13 November 2019
|
|
NEC ECC: Quotations under NEC3 ECC - for subcontracted elements
|
|
1
|
605
|
5 November 2019
|
|
NEC ECC: Under Option B, how is Defined Cost applied to a compensation event?
|
|
1
|
715
|
1 November 2019
|
|
NEC ECC: Option C - Expenses Disallowed
|
|
1
|
635
|
30 October 2019
|
|
NEC ECC: What exactly should be included within the fee?
|
|
1
|
653
|
29 October 2019
|
|
NEC ECC: People Defined Cost Rates
|
|
2
|
2427
|
20 October 2019
|
|
NEC ECC: Option B - Defined Cost for CE Assessment
|
|
1
|
661
|
7 October 2019
|
|
NEC ECC: What is included in 'buying & leasing land' within schedule of cost components?
|
|
1
|
758
|
3 October 2019
|
|
NEC3 ECC: Option C - The meaning of "Directly Employed" under People in SOCC
|
|
3
|
576
|
23 September 2019
|
|
NEC ECS: Subcontract Working Area Differs from Head Contract
|
|
1
|
474
|
18 September 2019
|
|
NEC ECC: Normal Place of Work
|
|
1
|
768
|
3 September 2019
|
|
NEC PSC: Option E staff rates
|
|
2
|
1870
|
2 September 2019
|
|
NEC ECC: Can you be paid for working outside of the Working Areas?
|
|
1
|
1629
|
4 July 2019
|
|
NEC ECC: Do Labour rates in the SSOCC include the direct fee?
|
|
3
|
959
|
3 May 2019
|