NEC ECC: Conflict between NEC3 Option C clauses 61.1 and 61.3 - PM and Contractor CEs?
|
|
1
|
1947
|
18 May 2020
|
NEC ECC: Coronavirus change in law - X2 (Scotland)
|
|
1
|
687
|
18 May 2020
|
NEC3: Should the employer be expected to revise quotations based on the latest schedules (as claimed by the contractor) or should clause 65.2 apply and the quotation remain as previously agreed?
|
|
1
|
449
|
18 May 2020
|
NEC ECC: Items missed from fixed price
|
|
2
|
517
|
18 May 2020
|
NEC: What is the best form of contract for a £400k project?
|
|
1
|
489
|
18 May 2020
|
NEC ECC: Late quotations
|
|
1
|
951
|
18 May 2020
|
NEC4 Value Engineering / Contractor's Proposal
|
|
1
|
1681
|
15 May 2020
|
NEC ECC: Compensation Event Assessment when Contractor delays another
|
|
3
|
611
|
14 May 2020
|
NEC3 Option E Clause 31 Z Clause
|
|
1
|
641
|
14 May 2020
|
NEC4 - Option A, X15 included. Value Engineering? Changing to Scope? Compensation Event?
|
|
1
|
1406
|
14 May 2020
|
NEC ECC: Clause 63.1 - "Should have been instructed...."
|
|
1
|
794
|
14 May 2020
|
NEC ECC - Time Risk Allowance and Changes to Critical Path
|
|
1
|
542
|
12 May 2020
|
NEC ECC: Working Area - In light of Covid-19 should it be changed to include dwellings or would it invite more problems?
|
|
1
|
758
|
12 May 2020
|
NEC ECC: Covid-19, would X2 be a valid reason to notify and be able to claim cost as a CE?
|
|
1
|
449
|
12 May 2020
|
NEC3 Option C disallowed Subcontractor costs
|
|
1
|
807
|
12 May 2020
|
NEC ECC: Whose liability are items missing on thE activity schedule under option A?
|
|
1
|
2088
|
11 May 2020
|
NEC ECC: Option A , Error in pricing - X15 is incorporated in the contract
|
|
5
|
1011
|
11 May 2020
|
NEC ECC: Prevention wording compared to NEC3
|
|
3
|
791
|
11 May 2020
|
NEC3 ECC Option A Contract - Contractor Delay
|
|
1
|
503
|
11 May 2020
|
NEC ECC: Payment certificates after Completion
|
|
1
|
759
|
9 May 2020
|
NEC ECC: Option A with Options X11 incorporated
|
|
1
|
1307
|
9 May 2020
|
NEC TSC: COVID Relief under NEC4
|
|
1
|
568
|
7 May 2020
|
NEC - Most appropriate form of contract(s) for the provision of temporary works/services
|
|
1
|
534
|
6 May 2020
|
NEC ECC: Retention on contracts
|
|
1
|
940
|
6 May 2020
|
NEC ECC: Option A - Change of supplier due to Covid 19
|
|
3
|
475
|
5 May 2020
|
NEC ECC: Who carries the risk when a subcontractor goes into administration
|
|
1
|
970
|
4 May 2020
|
NEC ECC: What happens if the Projects Manager rejects a compensation event quotation?
|
|
1
|
1644
|
4 May 2020
|
NEC ECC: Can bill of quantity rates be changed by agreement?
|
|
1
|
716
|
4 May 2020
|
NEC ECC: Can a CE be issued to omit works from Works Information if a CE was issued in error for this item of work?
|
|
1
|
542
|
4 May 2020
|
NEC ECC: Option B - Can the contractor ask to re-price the BoQ
|
|
1
|
1234
|
4 May 2020
|