ECC Opt A;
Coming to the end of a couple of jobs where CE’s have altered the critical path on the programme for acceptance.
For example, what used to be critical was a concrete hard standing that was weather dependent. Now, due to changes in the WI the landscaping duration has increased and become critical.
The original critical path through the concrete hard standing would have had risk identified in it as the TRA. Prior to it becoming critical landscaping had no TRA identified.
Now that it is critical is it unreasonable to add a time risk to it ? Or should each individual task on previous programmes have an element of TRA identified in case they become critical ?
Specific example possibly not relevant as there isn’t much risk to the landscaping but in principal if the specific tasks were altered, how should this be managed ?