|
JCT ICD 16 - Contractor has not priced specified item
|
|
0
|
352
|
14 October 2021
|
|
Jct minor works building contract 2016
|
|
2
|
1017
|
28 September 2021
|
|
JCT16 - Employer's Requirements (Guide)
|
|
2
|
556
|
27 September 2021
|
|
JCT Minor works further extension of time for variations
|
|
1
|
1518
|
24 September 2021
|
|
JCT D&B 2016 - Sectional Completion Delays and L&E
|
|
1
|
474
|
24 September 2021
|
|
JCTDB2016 - Conflict between contract particulars and ERs
|
|
3
|
634
|
9 September 2021
|
|
Contractor orders, increased cost and client position
|
|
3
|
438
|
18 August 2021
|
|
Issuing an Architects Instruction before Costs/ Programme impact have been provided
|
|
2
|
789
|
22 July 2021
|
|
ICC Term Version 2011 - Communications in writing (Cl. 1(6)
|
|
2
|
359
|
20 July 2021
|
|
Certificate of making good defects
|
|
3
|
1178
|
2 July 2021
|
|
JCT: Acceleration & Pre-Agreed Adjustment
|
|
0
|
987
|
17 June 2021
|
|
JCT DB 2016 Material on site procedure
|
|
1
|
445
|
4 June 2021
|
|
JCT 5 day payment issue
|
|
2
|
1212
|
22 April 2021
|
|
Webinar - Overview of Payment Provisions under JCT D&B Contract - Timing and Amounts Due
|
|
2
|
388
|
15 April 2021
|
|
NEC3 PSC revised programme rejection
|
|
1
|
629
|
6 April 2021
|
|
JCT Design & Build Contract 2016 – Supply Of Documents
|
|
1
|
650
|
16 March 2021
|
|
JCT DB Sub 2016
|
|
3
|
978
|
8 March 2021
|
|
JCT Consultancy Agreement (Public Sector) Annex A
|
|
0
|
395
|
28 January 2021
|
|
Completion Date at risk
|
|
2
|
436
|
18 February 2021
|
|
JCT ICD 2016 - Deferment of posession
|
|
3
|
1493
|
4 February 2021
|
|
JCT D&B 2016 Cost Variation
|
|
2
|
710
|
6 January 2021
|
|
JCT Contracts - Advance Payment
|
|
1
|
1007
|
26 November 2020
|
|
JCT D&B 2016 (Unamended)
|
|
2
|
464
|
20 November 2020
|
|
JCT Framework Agreement and Consultancy Agreement (Public Sector)
|
|
3
|
565
|
17 November 2020
|
|
JCT SBC Without Quants contract but client wants to add D&B variation
|
|
1
|
492
|
2 September 2020
|
|
JCT D&B Design Responsibility
|
|
2
|
1087
|
26 August 2020
|
|
Working to latest Instruction
|
|
2
|
461
|
4 August 2020
|
|
JCT: What is the C1 Replacement Schedule and should the Contract Particulars be completed?
|
|
1
|
3959
|
17 July 2020
|
|
JCT D&B16: What rights are available during defects liability period and Contractors obligation after termination?
|
|
1
|
1157
|
15 July 2020
|
|
JCT: If the EA fails to deal with an extension of time within the period set out does the employer loose entitlement to L&AD's?
|
|
2
|
1906
|
15 July 2020
|