The Client is undertaking refurbishment works in an office under JCT ICD 16. Works are currently progressing.
The provision of lockers are included in the contract however locks were not.
The Architect has issued an instruction to add the specific locks.
The Contractor has now placed the order for the lockers and has come back saying that there has been an increase in cost of the lockers since tender.
Does the Client have to incur the extra over cost of the lockers?