Webinar - Control of the Quality under JCT D&B Contract
|
|
4
|
572
|
23 December 2022
|
PQS approving a variation and instructing to proceed - but not agreeing the cost
|
|
1
|
571
|
1 December 2022
|
Extension of Time - L&E Claim
|
|
0
|
443
|
16 November 2022
|
Valuing Sub-Subcontract Costs
|
|
0
|
380
|
3 November 2022
|
JCT D&B 2016 - Novated Consultant Disagreement
|
|
1
|
337
|
2 November 2022
|
JCT D&B 2016 Relevant Matter Clauses
|
|
4
|
1182
|
28 October 2022
|
JCT contract used for a demolition project
|
|
3
|
1188
|
18 October 2022
|
JCT2016DB - Contractors Design Documents
|
|
2
|
585
|
10 October 2022
|
Re-Sequencing/Speeding up to minimise delay
|
|
0
|
428
|
30 August 2022
|
JCT Design and Build
|
|
0
|
375
|
3 August 2022
|
JCT D&B 2016 and sub-contractors
|
|
1
|
821
|
28 July 2022
|
JCT DB 2016 Corresponding Subcontract
|
|
1
|
463
|
27 July 2022
|
Delayed Access JCT SBC/Q 2016
|
|
0
|
701
|
7 July 2022
|
JCT Major Projects - discrepancy in Period for Completion
|
|
1
|
389
|
22 June 2022
|
Changes in Legislation
|
|
3
|
808
|
19 May 2022
|
JCT D&B 2016 - Uplift to service provider costs included in CSA
|
|
1
|
433
|
9 May 2022
|
Contractor Claim for Increased Costs under Loss and Expense
|
|
1
|
492
|
25 April 2022
|
Return visit loss & expense
|
|
1
|
635
|
25 April 2022
|
Webinar - Default, Repudiation, Insolvency and Termination Under JCT D&B
|
|
5
|
510
|
7 April 2022
|
JCT Design & Build - Potential Contractor Insolvency
|
|
1
|
496
|
6 April 2022
|
Webinar - Indemnity and Insurance under JCT D&B - Public Liability and Works Insurance
|
|
9
|
576
|
1 April 2022
|
JCT DB LD's & Payless
|
|
2
|
380
|
22 March 2022
|
JCT Statutory Undertaker Delay or Employer Impediment?
|
|
2
|
937
|
18 March 2022
|
Design Changes to Fitted Furniture Package
|
|
2
|
463
|
17 March 2022
|
JCTDB16 - Supplemental Provision 2 (Contractors Estimates)
|
|
1
|
527
|
18 February 2022
|
JCT DB 16 & Deferment of Site Possession
|
|
3
|
1601
|
11 February 2022
|
Liquidated Damages
|
|
2
|
592
|
21 January 2022
|
JCT Extensions of Time
|
|
2
|
661
|
4 January 2022
|
JCT SBC with CDP - Should Variation Rates for materials/ labour be based on tender date?
|
|
2
|
596
|
21 December 2021
|
JCT Copyright clauses
|
|
3
|
542
|
7 December 2021
|