About the JCT Contracts category
|
|
0
|
571
|
27 February 2020
|
JCT (ICD) 2016 Inconsistency of documents - Rectification Period
|
|
1
|
411
|
15 April 2024
|
Webinar - Consequences of failing to complete the works before the completion date and LADs under JCT D&B Contract
|
|
11
|
1718
|
6 March 2024
|
Webinar - Overview of Partial Possession and Practical Completion under JCT D&B Contract
|
|
10
|
928
|
28 February 2024
|
Webinar - Contractor Obligations under JCT D&B Contract for Subcontracting and H&S
|
|
2
|
291
|
16 February 2024
|
Webinar - Understanding Contracts Documents and how they Work Together
|
|
6
|
664
|
16 February 2024
|
Webinar - Contractor Obligations under JCT D&B Contract - Design and Quality Standards
|
|
9
|
780
|
16 February 2024
|
Webinar - Overview of the JCT Design and Build Contract
|
|
4
|
548
|
16 January 2024
|
JCT D&B SFC Time at large
|
|
1
|
368
|
28 November 2023
|
JCT ICD16 - Defect found after rectification period, Contractor unwilling to correct
|
|
2
|
196
|
24 November 2023
|
JCT retention release but more work keeps on being instructed
|
|
2
|
217
|
23 November 2023
|
Webinar - Overview of Payment Provisions under JCT D&B Contract - Listed items and deductions
|
|
5
|
653
|
22 November 2023
|
Reckoning Days and Pay Less Notices
|
|
2
|
482
|
20 November 2023
|
Design manufacturer and supply on a JCT
|
|
0
|
259
|
3 December 2022
|
Payment of Pro-Forma Invoices
|
|
0
|
297
|
7 March 2023
|
JCT ICSub/A 2016 Intermediate Sub-Contract Article 3A; Sub-Contract Sum & Final Sub-Contract Sum
|
|
4
|
258
|
18 October 2023
|
Webinar - Control of the Works by Employer’s Agent, Site Manager, Contractor and Employer under JCT D&B Contract
|
|
3
|
1081
|
4 October 2023
|
JCT Fluctuations
|
|
3
|
204
|
20 September 2023
|
JCT D&B16 SC Deferment of possession
|
|
2
|
305
|
29 August 2023
|
JCT Design And Build - Lump Sum - Client Omissions
|
|
1
|
373
|
12 July 2023
|
JCT Sub-Contract SBCSub/A - Subcontractor Delays
|
|
1
|
233
|
27 June 2023
|
Webinar - Understanding Key Documents of a JCT Design and Build Contract
|
|
4
|
454
|
19 June 2023
|
Webinar - Understanding What Sums Properly Due JCT Design & Build Contract Part 2 - Loss and Expense Claims
|
|
5
|
519
|
7 June 2023
|
Release of retention monies
|
|
1
|
323
|
6 June 2023
|
JCTSBC2016 - Contractor's Design (Recitals 11 & 12)
|
|
0
|
286
|
22 May 2023
|
Webinar - An Introduction to the Extensions of Time Provisions under JCT D&B Contract
|
|
10
|
504
|
13 April 2023
|
JCT D&B 2016 Prolongation Prelims
|
|
1
|
406
|
10 February 2023
|
Contract execution - Are wet signatures a legal requirement?
|
|
1
|
340
|
18 January 2023
|
JCT Final Account
|
|
2
|
938
|
16 January 2023
|
Construction Programmes
|
|
3
|
487
|
15 January 2023
|