Welcome to ReachBack
|
|
1
|
2272
|
28 November 2021
|
NEC3, Option C - Schedule of Cost Components
|
|
1
|
8
|
19 March 2024
|
Unimplemented CE's
|
|
2
|
112
|
18 March 2024
|
NEC 3, Option B
|
|
2
|
123
|
18 March 2024
|
Release Notes up to 2024-03-17 Contract Management Sprint 85
|
|
0
|
18
|
18 March 2024
|
Release Notes up to 2024-03-02 Contract Management Sprint 84
|
|
0
|
19
|
18 March 2024
|
NEC3 ECC: Can the quantities of a CE for Option B be remeasured?
|
|
4
|
3124
|
18 March 2024
|
NEC3 Option B - Clause 60.4
|
|
8
|
114
|
18 March 2024
|
NEC3, Option B - BQ Item and Omitted Item
|
|
0
|
30
|
18 March 2024
|
Cost deduction for defect that was not notified
|
|
0
|
34
|
16 March 2024
|
NEC3 Option B Clause 60.6
|
|
0
|
51
|
16 March 2024
|
Payless Notice Requirements
|
|
2
|
58
|
15 March 2024
|
NEC4 - Take-over Cl35.2 & Liabilities under Cl80.1
|
|
2
|
98
|
15 March 2024
|
NEC4 - CE to reduce scope
|
|
1
|
147
|
8 March 2024
|
NEC 4 Option E - Bespoke Fee clause
|
|
1
|
106
|
8 March 2024
|
Does the SSCC need to be comprehensive?
|
|
6
|
138
|
8 March 2024
|
Webinar - Consequences of failing to complete the works before the completion date and LADs under JCT D&B Contract
|
|
11
|
1380
|
6 March 2024
|
NEC 4 Option A - Extensive Change in the scope of works
|
|
5
|
194
|
6 March 2024
|
NEC 4 - Use of X20
|
|
0
|
117
|
5 March 2024
|
Built Connections 2024 - NEC User Group Conference
|
|
0
|
119
|
4 March 2024
|
Webinar - Overview of Partial Possession and Practical Completion under JCT D&B Contract
|
|
10
|
743
|
28 February 2024
|
Release Notes upto 2024-02-28 Academy
|
|
0
|
146
|
28 February 2024
|
Programme implications of a PMI issued as a result of late design
|
|
1
|
166
|
27 February 2024
|
NEC3 Option E - Contractor use of vehicles/transportation
|
|
2
|
169
|
27 February 2024
|
Option C Deep excavation to the lighting columns
|
|
3
|
410
|
23 February 2024
|
CE's on Option A Contract
|
|
4
|
539
|
23 February 2024
|
NEC3 Option A Subcontract - Defined Costs: What should be included in the agreed hourly rate for a CE?
|
|
2
|
1010
|
23 February 2024
|
Compensation Events in Option A applications for payment
|
|
5
|
560
|
23 February 2024
|
Increase in materials unit cost due to reduced Scope
|
|
3
|
423
|
23 February 2024
|
NEC3 ECC - Option B - Remeasurement Basis
|
|
5
|
628
|
23 February 2024
|