Working with JCT D&B - What would be the best course of action, contractually, when a contractor has not yet submitted all required bonds or collateral warranties?
Related topics
| Topic | Replies | Views | Activity | |
|---|---|---|---|---|
| Webinar - Understanding Key Documents of a JCT Design and Build Contract | 4 | 508 | 19 June 2023 | |
| A bills of quantities states that no certificates will be issued until the contractor has provided a performance bond. After six weeks no performance bond has been produced, but the contractor states that the architect is obliged to certify. Is this corre | 1 | 343 | 5 February 2013 | |
| With regards to construction contracts, are collateral warranties optional for architects? | 1 | 427 | 4 February 2013 | |
| Webinar - Design and Build Contracts: An overview of the JCT and NEC | 6 | 634 | 31 January 2023 | |
| Sub-Contractor's Proposals | 1 | 550 | 30 November 2021 |