NEC ECC: Can somebody tell me why retention isn't used with option F on NEC Contracts?
|
|
1
|
626
|
22 January 2020
|
NEC4 ECC Option A Section 8 Liabilities and Insurance - liabilities not listed as either Client's or Contractor's
|
|
1
|
1055
|
12 November 2019
|
NEC 3 Option Clause 52.1
|
|
1
|
752
|
31 October 2019
|
NEC ECC: Can an Employer trigger adjudication
|
|
2
|
547
|
4 October 2019
|
NEC ECC: ECI (NEC3) for an Option A main Works
|
|
1
|
1115
|
2 October 2019
|
NEC TSC: Non-Standard Price List Items
|
|
2
|
968
|
20 September 2019
|
NEC ECC & TSC: Terminology difference for Options A&C between ECC and TSC
|
|
1
|
854
|
18 September 2019
|
NEC AC: What are the limitations of using the NEC4 Alliance Contract as a Framework?
|
|
1
|
680
|
23 August 2019
|
NEC3 ECC: Where in NEC option C, can I establish who holds responsibility for the design? (I.e D&B or Traditional)
|
|
1
|
483
|
16 August 2019
|
NEC3 ECC: iIs the contractor entitled to payment for remedial works and loses and expenses as this event is to delay the contract?
|
|
1
|
653
|
16 August 2019
|
NEC ECC: Option A - Activity Schedule: Can a Client ask a Contractor to change activities for their own benefit?
|
|
2
|
694
|
25 July 2019
|
NEC ECC: Option A- Accepting subcontractors
|
|
1
|
550
|
12 July 2019
|
NEC ECC: Switching price from Option E to Option A
|
|
1
|
617
|
26 June 2019
|
NEC ECC: Option A quotation for an Option E contract?
|
|
1
|
429
|
18 June 2019
|
NEC ECC: How to contractually Include Tender Qualifications and TQ responses
|
|
6
|
1526
|
2 May 2019
|
NEC ECS: Option A Subcontract - Negative CE and Fee Percentages
|
|
5
|
1656
|
4 April 2019
|
NEC ECS: Subcontract Option A - No Clause 32 Programme
|
|
1
|
601
|
3 April 2019
|
NEC ECC: Temporary change to the working area
|
|
1
|
751
|
29 March 2019
|
NEC ECC: specification from Works Information or Bill item
|
|
1
|
859
|
20 February 2019
|
NEC ECC: Works Information Abuse?
|
|
2
|
664
|
15 February 2019
|
NEC ECS: Error in BOQ and MoM description
|
|
2
|
725
|
9 February 2019
|
NEC ECC: Option D Remeasurement
|
|
3
|
2657
|
1 February 2019
|
NEC ECC: Option C - Can non-project specifIc training costs be disallowed?
|
|
1
|
949
|
14 January 2019
|
NEC ECC: Can several pricing options be combined under one contract
|
|
2
|
856
|
10 January 2019
|
NEC ECC. Agreed Direct Fee, is it audit-able under an option E contract?
|
|
1
|
439
|
21 December 2018
|
NEC ECC: What clause in the Option A can be used in an Early Warning
|
|
2
|
567
|
22 October 2018
|
NEC ECC: option B re-measure quantity as zero
|
|
3
|
739
|
19 October 2018
|
NEC ECC: Disallowed Costs for stand down at Contractor's fault
|
|
1
|
1256
|
19 October 2018
|
NEC ECC: Delay Damage liability to Contractor when Employer cannot give access to the network
|
|
2
|
868
|
11 May 2018
|
NEC ECC: Is delaying Contractor payments on their option A activity schedule recoverable as a compensation event?
|
|
1
|
570
|
13 March 2018
|