|
NEC4 - Retention
|
|
1
|
552
|
1 April 2022
|
|
NEC Design Liability
|
|
3
|
863
|
24 March 2022
|
|
NEC ECSC: Who runs risk of items missed off the Price List?
|
|
2
|
1491
|
15 March 2022
|
|
Sectional Completion and Delay Damages
|
|
2
|
521
|
11 March 2022
|
|
Professional Service Subcontract - Why no 'Short' version?
|
|
4
|
962
|
7 March 2022
|
|
Labour Only Sub-Contractors
|
|
3
|
799
|
4 March 2022
|
|
Removing performance bond post contract NEC3
|
|
2
|
566
|
4 February 2022
|
|
Can the PM expedite take over?
|
|
3
|
470
|
2 February 2022
|
|
NEC 3 Option A - Design Delay - Preliminaries
|
|
2
|
644
|
27 January 2022
|
|
NEC3 ECSC: What are the main differences between long and short form ECC
|
|
2
|
5735
|
14 January 2022
|
|
Format of diagrams in NEC4 Scope
|
|
2
|
614
|
7 January 2022
|
|
Replacement of Key Person
|
|
2
|
1895
|
5 January 2022
|
|
NEC 3 Option E with zero LAD
|
|
1
|
637
|
10 December 2021
|
|
How does the Project Manager or the Contractor notify of an early warning?
|
|
2
|
1104
|
16 November 2021
|
|
NEC3 ECC Op A. Proposed change to works information
|
|
0
|
403
|
11 November 2021
|
|
NEC 3 CE Quotations
|
|
3
|
604
|
29 October 2021
|
|
NEC4 ECC Contractors savings for Option A
|
|
5
|
973
|
20 October 2021
|
|
Moving Materials between working areas
|
|
2
|
426
|
14 October 2021
|
|
NEC4 ECC errors in Accepted Programme
|
|
1
|
1008
|
11 October 2021
|
|
Construction Management with the NEC Contract
|
|
3
|
1081
|
5 October 2021
|
|
NEC3 - Clause 36 Acceleration
|
|
2
|
515
|
23 September 2021
|
|
Missed Acceleration dates
|
|
3
|
531
|
10 September 2021
|
|
ECC Option A contract - Sub - Contractors
|
|
3
|
1231
|
27 August 2021
|
|
NEC4 Option B - Removal of Items (0 Quantified) in Bill
|
|
1
|
911
|
23 August 2021
|
|
Risk Allocation
|
|
4
|
593
|
30 July 2021
|
|
ECC Option C Contract - PM
|
|
1
|
772
|
27 July 2021
|
|
Webinar - Understanding the Contractor and Subcontractor's Obligations under NEC3 ECS
|
|
0
|
371
|
16 July 2021
|
|
The Site and the Working Area
|
|
2
|
1730
|
13 July 2021
|
|
Does a contract amendment need to take place when new plant items have been instructed under the contract and damages are to be included
|
|
4
|
475
|
29 June 2021
|
|
NEC 4 Option C , Subcontractor
|
|
3
|
558
|
14 June 2021
|