Nec3 risk reduction - how far does co-operation go
|
|
9
|
785
|
9 March 2023
|
Local / Central Government Contract Amendments
|
|
2
|
374
|
6 February 2023
|
NEC4 Professional Services Short Contract Additional Conditions
|
|
2
|
392
|
1 February 2023
|
NEC4 ECS - Main Contract Scope
|
|
1
|
344
|
19 January 2023
|
Clause 16.1 - Notice of Early Warning
|
|
1
|
1209
|
19 January 2023
|
Owned Equipment
|
|
4
|
401
|
18 January 2023
|
NEC3 Option A: Request for quotation through response to EWN
|
|
1
|
484
|
12 January 2023
|
NEC3 ECC - Access Following Take Over
|
|
1
|
470
|
12 January 2023
|
Scope Clarification under NEC4
|
|
1
|
679
|
22 December 2022
|
Risk - For Discussion
|
|
2
|
745
|
15 December 2022
|
Supervisor Defect Notices
|
|
2
|
493
|
6 December 2022
|
Client costs when Contractor accelerates because it is in delay
|
|
5
|
737
|
15 November 2022
|
When is a subcontractor a Subcontractor?
|
|
1
|
501
|
4 November 2022
|
NEC 4 Term Service Short Contract
|
|
2
|
847
|
19 October 2022
|
Are two signatures necessary from both companies to make a contract enforceable
|
|
2
|
504
|
5 October 2022
|
Work Instruction query
|
|
1
|
430
|
16 September 2022
|
People Rates for subcontracted staff on NEC4 Option C
|
|
4
|
748
|
15 September 2022
|
NEC ECC: When is "starting date" if contracts are signed late?
|
|
2
|
5917
|
2 September 2022
|
NEC Term Service Contract
|
|
1
|
483
|
26 August 2022
|
Working Area definition
|
|
5
|
615
|
17 August 2022
|
NEC4 TSC Option A - How to set total of the prices with unknown quantities
|
|
1
|
659
|
17 August 2022
|
Import Taxes - Defined Cost or Other Amounts?
|
|
1
|
475
|
15 June 2022
|
NEC 3 SoCC - Bonus & Incentive Payments or Disallowed Cost?
|
|
2
|
737
|
3 May 2022
|
NEC4 - Retention
|
|
1
|
521
|
1 April 2022
|
NEC Design Liability
|
|
3
|
780
|
24 March 2022
|
NEC ECSC: Who runs risk of items missed off the Price List?
|
|
2
|
1379
|
15 March 2022
|
Sectional Completion and Delay Damages
|
|
2
|
491
|
11 March 2022
|
Professional Service Subcontract - Why no 'Short' version?
|
|
4
|
849
|
7 March 2022
|
Labour Only Sub-Contractors
|
|
3
|
697
|
4 March 2022
|
Removing performance bond post contract NEC3
|
|
2
|
538
|
4 February 2022
|