|
NEC4 BoQ - Incorrect Unit of Measure
|
|
1
|
306
|
28 April 2023
|
|
NEC Option B Prelims (Planned Completion or Contract Completion)
|
|
1
|
572
|
22 March 2023
|
|
NEC4 engineering and construction short subcontract
|
|
3
|
421
|
13 March 2023
|
|
Nec3 risk reduction - how far does co-operation go
|
|
9
|
797
|
9 March 2023
|
|
Local / Central Government Contract Amendments
|
|
2
|
376
|
6 February 2023
|
|
NEC4 Professional Services Short Contract Additional Conditions
|
|
2
|
422
|
1 February 2023
|
|
NEC4 ECS - Main Contract Scope
|
|
1
|
359
|
19 January 2023
|
|
Clause 16.1 - Notice of Early Warning
|
|
1
|
1465
|
19 January 2023
|
|
Owned Equipment
|
|
4
|
425
|
18 January 2023
|
|
NEC3 Option A: Request for quotation through response to EWN
|
|
1
|
499
|
12 January 2023
|
|
NEC3 ECC - Access Following Take Over
|
|
1
|
520
|
12 January 2023
|
|
Scope Clarification under NEC4
|
|
1
|
716
|
22 December 2022
|
|
Risk - For Discussion
|
|
2
|
888
|
15 December 2022
|
|
Supervisor Defect Notices
|
|
2
|
512
|
6 December 2022
|
|
Client costs when Contractor accelerates because it is in delay
|
|
5
|
777
|
15 November 2022
|
|
When is a subcontractor a Subcontractor?
|
|
1
|
529
|
4 November 2022
|
|
NEC 4 Term Service Short Contract
|
|
2
|
912
|
19 October 2022
|
|
Are two signatures necessary from both companies to make a contract enforceable
|
|
2
|
510
|
5 October 2022
|
|
Work Instruction query
|
|
1
|
437
|
16 September 2022
|
|
People Rates for subcontracted staff on NEC4 Option C
|
|
4
|
771
|
15 September 2022
|
|
NEC ECC: When is "starting date" if contracts are signed late?
|
|
2
|
6290
|
2 September 2022
|
|
NEC Term Service Contract
|
|
1
|
509
|
26 August 2022
|
|
Working Area definition
|
|
5
|
702
|
17 August 2022
|
|
NEC4 TSC Option A - How to set total of the prices with unknown quantities
|
|
1
|
745
|
17 August 2022
|
|
Import Taxes - Defined Cost or Other Amounts?
|
|
1
|
485
|
15 June 2022
|
|
NEC 3 SoCC - Bonus & Incentive Payments or Disallowed Cost?
|
|
2
|
763
|
3 May 2022
|
|
NEC4 - Retention
|
|
1
|
538
|
1 April 2022
|
|
NEC Design Liability
|
|
3
|
815
|
24 March 2022
|
|
NEC ECSC: Who runs risk of items missed off the Price List?
|
|
2
|
1438
|
15 March 2022
|
|
Sectional Completion and Delay Damages
|
|
2
|
500
|
11 March 2022
|