Under NEC4 Option B, would an incorrect unit of Measure stated in the BoQ give rise to a Compensation Event?
2 Likes
Yes, under clause 60.6 the PM is required to give an instruction to correct a mistake in the BoQ and this is a compensation event.
2 Likes