Contractor has entered in to an NEC4 Option A contract.
Drawings were taken-off at tender and submitted price was based upon this. Upon commencing and reconciling the works, it has become apparent that the stated scale is incorrect by a factor of 5%. This has resulted in works being undertaken to a greater extent than what was originally envisaged.
The Contractor is claiming a 60.1 (1) compensation event for a change to the scope upon this scale error being realised and acknowledged (there is no drawing note to say ‘do not scale’, as is sometimes the case)
The Project Manager is stating the contract is an Option A fixed price (which the Contractor takes the risk on quantities) and there is not a change to the Scope, as the although the scale error is acknowledged, no revised drawing has been issued (or is required).
Should the Contractor be entitled to a compensation event or is the Project Manager correct in rejecting this?