Can an adjudicator reopen an implemented Compensation Event, if the Contractor is unhappy at a later date with their implemented assessment communicated to the subcontractor? The contract is an NEC3 Option C. The compensation event implementation and W2 clauses are unamended.
Yes he can. Officially, an adjudicator is the only one who can reopen an implemented compensation event.