JCT D&B16: Is it feasible to amend the Contract terms?
|
|
2
|
572
|
8 July 2020
|
JCT DB16: In the event of insolvency, can a Employer damage the Contractor's property?
|
|
1
|
528
|
8 July 2020
|
JCT D&B Contract EOT Query
|
|
1
|
586
|
6 July 2020
|
JCT: Can i refuse to action a variation instruction on the grounds of incomplete information being provided therein
|
|
1
|
534
|
23 June 2020
|
JCT: Conflict in the measurement of variations
|
|
4
|
715
|
22 June 2020
|
JCT: New handover dates and potential EOT?
|
|
1
|
609
|
22 June 2020
|
JCT DB16: What is a Contractor entitled to include in their Contractor's Application?
|
|
1
|
547
|
22 June 2020
|
JCT: No response on EOT / Variations
|
|
1
|
1044
|
22 June 2020
|
JCT: Applied for EOT and no response
|
|
1
|
707
|
19 June 2020
|
JCT DB16: What is a Contractor entitled to include in their Contractor's Application?
|
|
2
|
525
|
18 June 2020
|
JCT DB16: If a contractor brought on to site materials due to a later potential supply issue does this come under "on-site prematurely" rule and therefore he would not get paid?
|
|
1
|
657
|
17 June 2020
|
JCT: SB 2016 is the contractor not providing a quotation in a timely manner reason for the employer to apportion blame on the contractor for project delay
|
|
1
|
1653
|
4 June 2020
|
JCT MW2016 - Additional works not instructed
|
|
1
|
522
|
3 June 2020
|
JCT: Claims for Covid 19 under contract
|
|
2
|
622
|
29 May 2020
|
JCT: Is the risk register a contract document?
|
|
1
|
1485
|
12 May 2020
|
JCT: Contractor's Design Portion
|
|
2
|
1043
|
6 May 2020
|
JCT: Mechanism for agreeing general variations
|
|
3
|
1420
|
1 May 2020
|
JCT: Practical Completion for Sectional Completion Contracts
|
|
2
|
763
|
23 April 2020
|
JCT: Correct use of Named Sub-Contractor procurement under the JCT ICD
|
|
1
|
517
|
21 April 2020
|
JCT: SBC 16 - What elements does retention apply to:
|
|
1
|
661
|
21 April 2020
|
JCT: Whats the main different between a traditional accelerate lump sum standard building contract and a design and build contract?
|
|
2
|
531
|
21 April 2020
|
JCT - Provisional Sum Issue - not defined in Articles
|
|
1
|
666
|
21 April 2020
|
JCT: How does the third recital in the JCT D&B contract compare with clause 2.14.2 (discrepancies in documents) regarding the precedecne of the ER's over the CP's?
|
|
2
|
2814
|
30 March 2020
|
JCT: What would be the correct procedure to place a site on temporary stop during corona virus shut down, without impacting either party
|
|
1
|
551
|
26 March 2020
|
JCT 2016 w/Contractors Design - Correct valuation for reduced scope of works
|
|
1
|
389
|
18 March 2020
|
JCT: Contradictory provisions
|
|
1
|
659
|
18 March 2020
|
JCT: what is the process/requirement within JCT for getting subcontractors accepted?
|
|
1
|
712
|
18 March 2020
|
JCT: Statutory Undertakers - SBC/XQ 2016
|
|
1
|
525
|
23 January 2020
|
JCT: What happens if a Provisional Sum is too low?
|
|
1
|
1384
|
23 January 2020
|
JCT: DB16- Is the Employer required to inform the contractor that the application for payment is not valid
|
|
1
|
530
|
23 January 2020
|