JCT D&B16: Is it feasible to amend the Contract terms?
|
|
2
|
524
|
8 July 2020
|
JCT DB16: In the event of insolvency, can a Employer damage the Contractor's property?
|
|
1
|
478
|
8 July 2020
|
JCT D&B Contract EOT Query
|
|
1
|
538
|
6 July 2020
|
JCT: Can i refuse to action a variation instruction on the grounds of incomplete information being provided therein
|
|
1
|
480
|
23 June 2020
|
JCT: Conflict in the measurement of variations
|
|
4
|
657
|
22 June 2020
|
JCT: New handover dates and potential EOT?
|
|
1
|
540
|
22 June 2020
|
JCT DB16: What is a Contractor entitled to include in their Contractor's Application?
|
|
1
|
494
|
22 June 2020
|
JCT: No response on EOT / Variations
|
|
1
|
889
|
22 June 2020
|
JCT: Applied for EOT and no response
|
|
1
|
639
|
19 June 2020
|
JCT DB16: What is a Contractor entitled to include in their Contractor's Application?
|
|
2
|
467
|
18 June 2020
|
JCT DB16: If a contractor brought on to site materials due to a later potential supply issue does this come under "on-site prematurely" rule and therefore he would not get paid?
|
|
1
|
585
|
17 June 2020
|
JCT: SB 2016 is the contractor not providing a quotation in a timely manner reason for the employer to apportion blame on the contractor for project delay
|
|
1
|
1498
|
4 June 2020
|
JCT MW2016 - Additional works not instructed
|
|
1
|
491
|
3 June 2020
|
JCT: Claims for Covid 19 under contract
|
|
2
|
585
|
29 May 2020
|
JCT: Is the risk register a contract document?
|
|
1
|
1275
|
12 May 2020
|
JCT: Contractor's Design Portion
|
|
2
|
967
|
6 May 2020
|
JCT: Mechanism for agreeing general variations
|
|
3
|
1226
|
1 May 2020
|
JCT: Practical Completion for Sectional Completion Contracts
|
|
2
|
625
|
23 April 2020
|
JCT: Correct use of Named Sub-Contractor procurement under the JCT ICD
|
|
1
|
466
|
21 April 2020
|
JCT: SBC 16 - What elements does retention apply to:
|
|
1
|
555
|
21 April 2020
|
JCT: Whats the main different between a traditional accelerate lump sum standard building contract and a design and build contract?
|
|
2
|
483
|
21 April 2020
|
JCT - Provisional Sum Issue - not defined in Articles
|
|
1
|
593
|
21 April 2020
|
JCT: How does the third recital in the JCT D&B contract compare with clause 2.14.2 (discrepancies in documents) regarding the precedecne of the ER's over the CP's?
|
|
2
|
2334
|
30 March 2020
|
JCT: What would be the correct procedure to place a site on temporary stop during corona virus shut down, without impacting either party
|
|
1
|
511
|
26 March 2020
|
JCT 2016 w/Contractors Design - Correct valuation for reduced scope of works
|
|
1
|
341
|
18 March 2020
|
JCT: Contradictory provisions
|
|
1
|
587
|
18 March 2020
|
JCT: what is the process/requirement within JCT for getting subcontractors accepted?
|
|
1
|
530
|
18 March 2020
|
JCT: Statutory Undertakers - SBC/XQ 2016
|
|
1
|
477
|
23 January 2020
|
JCT: What happens if a Provisional Sum is too low?
|
|
1
|
1193
|
23 January 2020
|
JCT: DB16- Is the Employer required to inform the contractor that the application for payment is not valid
|
|
1
|
462
|
23 January 2020
|