JCT DB16: What is a Contractor entitled to include in their Contractor's Application?

Assuming Alternative B, can you confirm what a Contractor is entitled to include in their Contractor’s Application? Should it be works executed up to the Interim Valuation date, the date of their application or can they forecast up to the Due Date?

1 Like

Clause 4.13 states the valuation is calculated as at the Interim Valuation Date and it includes the value of work properly executed up until that point.