What happens when provisional sum is stated in contract sum analysis; but not defined in the Articles.
Especially as the JCT DB 2016 is a fixed price lump sum contract and the Employer does not have authority to reduce the contract sum analysis; only the ER’s
Surely the Prov Sums should be defied within the Articles as a separate schedule of items