Hi there, I’m writing a dissertation on a critical analysis of an extension of time.
In my particular project, the main contractor cited a relevant event as the late clarification of a floor finish which was a long lead item.
However, the floor finish has required clarification for a year prior and had not been pushed as an important RFI. Is there any cases of adjudication or something similar that reflects such a situation?
It feels as if the contractor has waited for a choice moment to claim an extension of time for a query they could have raised long before.