Defects after Completion
|
|
11
|
2195
|
9 March 2021
|
Webinar - FastDraft Compensation Events Masterclass
|
|
60
|
1711
|
17 October 2023
|
NEC3 Option A: Contractor is claiming Prolongation costs greater than his preliminary costs
|
|
12
|
6418
|
30 April 2018
|
NEC ECC: Client wants to issue a PMI for further works under a contract which has just finished
|
|
11
|
5893
|
6 March 2018
|
Employers Design Liability
|
|
14
|
1101
|
7 January 2021
|
Must the answers to Tender Clarification questions (pre-tender) be considered as part of the Contractual Documents once awarded?
|
|
10
|
3033
|
10 July 2018
|
Webinar - Contractor Obligations under JCT D&B Contract - Design and Quality Standards
|
|
9
|
780
|
16 February 2024
|
Nec3 risk reduction - how far does co-operation go
|
|
9
|
744
|
9 March 2023
|
EWN has been issued by Contractor regarding supply chain
|
|
10
|
1067
|
25 November 2021
|
Webinar - First Thursday Forum Live Q&A
|
|
13
|
899
|
2 December 2021
|
Assessment of CE quotation using defined cost for future works
|
|
10
|
563
|
29 May 2023
|
New Webinar - FastDraft Masterclass: Compensation Events
|
|
13
|
758
|
18 September 2022
|
NEC ECC: Imposing Sectional Delay Damages
|
|
10
|
2320
|
6 June 2019
|
Webinar - Consequences of failing to complete the works before the completion date and LADs under JCT D&B Contract
|
|
11
|
1718
|
6 March 2024
|
Webinar - FastDraft Early Warning Masterclass
|
|
10
|
850
|
28 May 2021
|
Webinar - Construction Cost Inflation
|
|
12
|
522
|
30 August 2022
|
Webinar - Payment and the Construction Act
|
|
13
|
849
|
22 February 2024
|
43.4 - Who pays for the costs of allowing the contractor access for correcting a Defect?
|
|
9
|
989
|
23 October 2021
|
Webinar - Overview of Partial Possession and Practical Completion under JCT D&B Contract
|
|
10
|
929
|
28 February 2024
|
New feature Released - Capturing WBS costs and reporting
|
|
16
|
654
|
21 December 2020
|
New feature - Tagging and associated notices
|
|
16
|
617
|
25 November 2020
|
Webinar - Introduction to Date of Possession and Completion under JCT D&B Contract
|
|
9
|
794
|
2 December 2021
|
New feature - Forecasting of total Defined Cost
|
|
14
|
560
|
3 February 2021
|
NEC ECSS: Consequence of failure by Contractor to respond to Subcontractor's compensation event within 1 week ECSS
|
|
9
|
683
|
23 May 2019
|
New feature Released - Smart custom links in main navigation panel
|
|
11
|
619
|
9 December 2020
|
Webinar - Indemnity and Insurance under JCT D&B - Public Liability and Works Insurance
|
|
9
|
566
|
1 April 2022
|
Webinar - An Introduction to the Extensions of Time Provisions under JCT D&B Contract
|
|
10
|
504
|
13 April 2023
|
NEC3 ECC: Supervisor - Roles and Responsibilities
|
|
1
|
3669
|
11 October 2017
|
NEC Option C - How to calculate a banded Pain/Gain calculation
|
|
2
|
21544
|
29 August 2015
|
NEC3 ECC: Can a compensation event be revisited to correct a mistake?
|
|
1
|
2408
|
28 August 2015
|
Does accepting a revised programme change the contract completion date?
|
|
2
|
5378
|
26 June 2014
|
Clause 63.5 - Contractor does not give an early warning of a compensation event
|
|
1
|
6117
|
17 November 2014
|
NEC3 ECC: How to apply subcontract fee percentages
|
|
6
|
17135
|
15 December 2023
|
Can X20 under NEC3 ECC be used to deduct money for poor performance under a KPI?
|
|
1
|
4040
|
14 June 2013
|
NEC ECC: How to calculate the total of the Prices under Option C?
|
|
1
|
6714
|
27 October 2017
|
Ukraine War - Impact on material prices
|
|
7
|
1867
|
12 June 2022
|
Under the NEC Contract option A, when do you apply the direct fee % and the Subcontracted fee percentage?
|
|
7
|
30194
|
4 March 2019
|
NEC ECC: Is the Client obliged under to pay for offsite materials if Vesting Certificate is provided?
|
|
2
|
7545
|
6 April 2017
|
NEC3 Direct fee percentage and subcontracted fee percentage
|
|
3
|
17550
|
10 February 2021
|
Can you summarise the key differences between NEC3 and NEC4?
|
|
1
|
13227
|
3 May 2017
|
NEC 3 & 4 SOCC - Fuel, Oils, Lubricants & Other Consumables used in relation to hired Equipment
|
|
1
|
627
|
5 January 2023
|
Is a Vesting Certificate required under Clause 70 of the un-amended NEC?
|
|
1
|
10161
|
4 February 2015
|
NEC3 Option B - Who carries risk of Quantities
|
|
8
|
14428
|
26 June 2014
|
What if the site investigation report is inaccurate and ground risk is with the contractor
|
|
2
|
413
|
30 May 2023
|
NEC4 ECC errors in Accepted Programme
|
|
1
|
873
|
11 October 2021
|
What are compensation events?
|
|
1
|
856
|
15 September 2012
|
Contractor's Share
|
|
2
|
683
|
25 July 2022
|
NEC ECC: What are hand tools not powered by compressed air?
|
|
3
|
10365
|
29 November 2018
|
NEC ECC: Working Area Overhead Percentages - Inclusions/ exclusions
|
|
1
|
8135
|
21 May 2017
|
Procurement: What is CPV?
|
|
1
|
776
|
18 September 2015
|