Is a Vesting Certificate required under Clause 70 of the un-amended NEC?

We are working on a large framework and have the requirement to purchase high value materials that are stored off site. Is there a need for a vesting certificate as this is not mentioned in Clause 70. We have marked the materials for the Employer, we have also requested payment which has been made

2 Likes

The simple answer is ‘No’ providing it is not required under the contract either :

  • as an additional option Z clause to the existing requirements (which you seem to have fulfilled) in clause 70; or
  • somewhere in the Works Information.