About the Compensation Events category
|
|
0
|
657
|
27 February 2020
|
Option E Programmes
|
|
0
|
19
|
26 April 2024
|
NEC Option A Compensation Events with drawing revisions- How is Fee applied
|
|
1
|
39
|
26 April 2024
|
Planned Completion & Completion Date
|
|
0
|
40
|
23 April 2024
|
People Rates for Specialist Sub-contractor
|
|
0
|
39
|
23 April 2024
|
NEC3 - Cl.60.1.(8)
|
|
1
|
427
|
15 April 2024
|
NEC Option B 60.4
|
|
1
|
213
|
15 April 2024
|
NEC3 Option B Clause 60.6
|
|
1
|
320
|
25 March 2024
|
Reopening implemented Compensation Events
|
|
1
|
304
|
25 March 2024
|
NEC3, Option B - BQ Item and Omitted Item
|
|
1
|
241
|
25 March 2024
|
NEC 3, Option B
|
|
2
|
373
|
18 March 2024
|
NEC3 ECC: Can the quantities of a CE for Option B be remeasured?
|
|
4
|
3371
|
18 March 2024
|
NEC3 Option B - Clause 60.4
|
|
8
|
375
|
18 March 2024
|
NEC4 - CE to reduce scope
|
|
1
|
387
|
8 March 2024
|
Does the SSCC need to be comprehensive?
|
|
6
|
328
|
8 March 2024
|
NEC 4 Option A - Extensive Change in the scope of works
|
|
5
|
387
|
6 March 2024
|
Option C Deep excavation to the lighting columns
|
|
3
|
565
|
23 February 2024
|
CE's on Option A Contract
|
|
4
|
632
|
23 February 2024
|
NEC3 Option A Subcontract - Defined Costs: What should be included in the agreed hourly rate for a CE?
|
|
2
|
1113
|
23 February 2024
|
Compensation Events in Option A applications for payment
|
|
5
|
731
|
23 February 2024
|
Increase in materials unit cost due to reduced Scope
|
|
3
|
476
|
23 February 2024
|
NEC3 ECC - Option B - Remeasurement Basis
|
|
5
|
715
|
23 February 2024
|
Last Accepted Programme
|
|
2
|
482
|
23 February 2024
|
How to define "open market rate"?
|
|
3
|
388
|
23 February 2024
|
NEC4 ECC Option A Effect on Defined Cost
|
|
2
|
292
|
23 February 2024
|
Damages in CE quotations
|
|
3
|
623
|
23 February 2024
|
Application of Fee to X1 PAF Calculation
|
|
1
|
344
|
12 January 2024
|
NEC 3 omission of scope
|
|
3
|
383
|
23 December 2023
|
Equipment Durations
|
|
1
|
261
|
22 December 2023
|
Zero value compensation events....?
|
|
3
|
323
|
22 December 2023
|