About the SOCC SSOCC category
|
|
0
|
403
|
27 February 2020
|
PSC4 - People or Subcontractor
|
|
1
|
44
|
25 April 2024
|
What does the term Subsistence cover in terms of Defined Costs under SOCC
|
|
0
|
394
|
13 October 2022
|
NEC ECS Option A - SSOCC - Items not listed
|
|
1
|
237
|
27 August 2023
|
NEC ECC Option C - Equipment rates
|
|
2
|
1852
|
23 July 2023
|
NEC3 - ECC3 Option A SSOCC - Contingency Provision in Quotation
|
|
5
|
437
|
23 July 2023
|
NEC3 ECC Option C: Equipment repair and maintenance
|
|
2
|
584
|
23 July 2023
|
NEC 3 & 4 SOCC - Fuel, Oils, Lubricants & Other Consumables used in relation to hired Equipment
|
|
1
|
627
|
5 January 2023
|
NEC4 Employers Liability in SoCC under People
|
|
2
|
783
|
24 March 2022
|
Payments made in relation to People for Pensions
|
|
2
|
592
|
29 November 2021
|
NEC3 - ECC - SOCC - Expenses
|
|
1
|
885
|
15 March 2021
|
NEC3 Supply Contract SOCC
|
|
2
|
496
|
23 February 2021
|
Sub contractor equipment cost
|
|
1
|
750
|
14 January 2021
|
NEC3 ECC - Shorter Schedule of Cost Components Percentages
|
|
2
|
3397
|
8 January 2021
|
NEC 3 SOCC - Medicine Reimbursements
|
|
1
|
503
|
4 January 2021
|
SSCC Equipment List - Non Existent
|
|
1
|
511
|
4 January 2021
|
Defined Cost - Percentages - Option A contract
|
|
1
|
723
|
31 December 2020
|
NEC3 ECC Option D – Schedule of Cost Components – Health Insurance
|
|
1
|
640
|
16 October 2020
|
NEC 3 - Headhunter's fee
|
|
1
|
888
|
16 October 2020
|
NEC3 ECC Schedule of Cost Compenents - Charges 4 - Specialist Services 43(h)
|
|
3
|
1576
|
4 September 2020
|
NEC4 ECC: Option C - Self Isolation covered under the SCC during Covid-19 period?
|
|
3
|
833
|
8 July 2020
|
NEC ECC: Change of CECA Rates When Pricing a Initial And Revised Compensation Event Quotations
|
|
1
|
709
|
3 July 2020
|
NEC ECC: Addition of fee to CECA Equipment Rates
|
|
2
|
2115
|
3 July 2020
|
NEC ECC: CECA Rates within a Compensation Event
|
|
2
|
1299
|
2 July 2020
|
NEC ECC: What if the Contractor installs something better than the Works Information?
|
|
1
|
449
|
26 June 2020
|
NEC ECC: How are Prices reviewed for a compensation event that is an instruction from the Employer?
|
|
1
|
588
|
26 June 2020
|
NEC ECC: Interpretation of NEC4 SOCC
|
|
1
|
1564
|
25 June 2020
|
NEC ECC: Same Subcontract fee percentage applied to subcontracts under option A and C?
|
|
2
|
902
|
16 June 2020
|
NEC ECC: Under an option C contract, how would items that have been instructed by the Project Manager be covered in the defined cost?
|
|
1
|
636
|
16 June 2020
|
NEC3 Option C disallowed Subcontractor costs
|
|
1
|
713
|
12 May 2020
|