Hi, I am currently working on a NEC 3 ECC option A contract.
we are currently assessing a Compensation Event using the Shorter Schedule of Cost Components and a differing of opinion has presented itself in relation to section 4 charges.
I was hoping the forum could give advice on this, in particular the following:
Bullet 1 - payments for the provision and use in the Working Areas of water, gas
and electricity. - Would items such as Generators/Solar panels for powering the site offices and equipment on site be covered here and within the people overhead %?
Bullet 3 - Catering and sanitation - As above, is the intention of this clause to state that canteens and toilets’ are included in the people overhead %?
I realize accommodation is excluded for the people overhead %, but unsure how far the definition of “accommodation” reaches.
Thank you in advance for any replies.