Webinar - Design and Build Contracts: An overview of the JCT and NEC
|
|
6
|
520
|
31 January 2023
|
Webinar - Impact of Sustainability Issues on Development and Construction
|
|
0
|
196
|
23 December 2022
|
NEC3: Project Managers Assessment
|
|
2
|
418
|
7 November 2022
|
Capabilities of the Contractor
|
|
2
|
395
|
3 November 2022
|
NEC3: Project Reporting (CVR's) - CL.32 V CL.31 Programme
|
|
3
|
571
|
19 October 2022
|
Stopping payment on a target contract: Option C
|
|
2
|
355
|
7 October 2022
|
Misalingment of activity schedule and works information
|
|
1
|
400
|
31 August 2022
|
Webinar - Construction Cost Inflation
|
|
12
|
510
|
30 August 2022
|
Value Engineering - NEC3
|
|
1
|
339
|
13 July 2022
|
Sectional Completion Query
|
|
3
|
398
|
8 July 2022
|
Quotation format for a subcontractor under NEC option A
|
|
0
|
338
|
29 June 2022
|
NEC 3: Option B - People fee
|
|
1
|
390
|
15 June 2022
|
Relationship with sectional completion dates and planned completion
|
|
1
|
406
|
12 May 2022
|
Site Conditions and NEC4 ESC Option B
|
|
1
|
411
|
9 May 2022
|
Option B (NEC3) Fee percentage
|
|
1
|
410
|
28 April 2022
|
Mitigation Within Clause 62 Impact Programmes
|
|
5
|
1166
|
20 April 2022
|
NEC3 ECC Part 3/6: How to produce and update your Programme,NEC3 Quality Management, Managing Defects and producing Good Works
|
|
0
|
285
|
7 April 2022
|
Issue of GC to add an additional scope against existing scope of an EI
|
|
0
|
326
|
5 April 2022
|
Quotation - legitimate or not?
|
|
2
|
465
|
31 March 2022
|
Criminal Assault on a Construction Project
|
|
0
|
428
|
17 January 2022
|
Acceptance via PMI
|
|
5
|
534
|
7 January 2022
|
Accepted Defects - No Quotation for Reduced Prices
|
|
2
|
533
|
7 January 2022
|
NEC4 Weather Event
|
|
2
|
460
|
7 January 2022
|
NEC3 TSC - Option A - use of People rates
|
|
2
|
553
|
7 January 2022
|
Webinar - NEC3 TSC (Part 2/6): Roles and responsibilities of the Service Manager and Contractor
|
|
2
|
386
|
8 December 2021
|
Prevention Event?
|
|
2
|
436
|
3 December 2021
|
Contingency Sums Option A NEC4
|
|
0
|
377
|
1 December 2021
|
NEC4 - Retention Alternatives
|
|
1
|
375
|
9 November 2021
|
30.2 Project Manager deciding Completion
|
|
0
|
334
|
30 October 2021
|
NEC4 ECC Contractors Design
|
|
0
|
290
|
7 October 2021
|