Is the contractor entitled to recovery of pricing the CE under the people costs of the SSCC. So are they entitled to QS time and planner time to assess cost and programme implication of the event?
Related topics
| Topic | Replies | Views | Activity | |
|---|---|---|---|---|
| NEC4 Opt A - Claiming for items not listed within the SSCC in a CE | 3 | 547 | 5 April 2023 | |
| NEC4 PSC - Changes to People Rates under SSoCC | 5 | 244 | 19 March 2025 | |
| NEC: ECC Option A - how do I assess Compensation Events when the Shorter Schedule of Cost Components does not include rates for People? | 1 | 4223 | 16 January 2016 | |
|
NEC Option A - Quotation cost
|
6 | 66 | 29 August 2025 | |
| What are the components to be included within the ssocc option A for peoples cost | 1 | 1154 | 5 December 2013 |