Is the contractor entitled to recovery of pricing the CE under the people costs of the SSCC. So are they entitled to QS time and planner time to assess cost and programme implication of the event?
Related topics
Topic | Replies | Views | Activity | |
---|---|---|---|---|
NEC4 Opt A - Claiming for items not listed within the SSCC in a CE | 3 | 526 | 5 April 2023 | |
NEC4 PSC - Changes to People Rates under SSoCC | 5 | 165 | 19 March 2025 | |
NEC: ECC Option A - how do I assess Compensation Events when the Shorter Schedule of Cost Components does not include rates for People? | 1 | 4193 | 16 January 2016 | |
What are the components to be included within the ssocc option A for peoples cost | 1 | 1147 | 5 December 2013 | |
NEC ECC: Completing Contract Data Part 2 Part 6 of NEC4 Option B | 1 | 768 | 28 October 2019 |