NEC3 PSC: Applying Indexation
|
|
2
|
955
|
20 May 2021
|
ECI X22 Managing Changes to Stage 2 Before the Notice to Proceed
|
|
1
|
613
|
17 February 2021
|
NEC4 X22 (ECI) and it's relationship with the Scope
|
|
2
|
1832
|
29 January 2021
|
NEC ECC: Use of Secondary Option X18
|
|
2
|
3821
|
21 September 2020
|
NEC ECC: Should we notify early warnings during stage 1 ECI?
|
|
1
|
696
|
16 July 2020
|
NEC3 TSC: What volume of reactive works can be carried out under an NEC3 TSC contract with no X19 clause
|
|
2
|
437
|
24 June 2020
|
NEC ECC: Collateral Warranty for Framework Agreement
|
|
1
|
542
|
18 June 2020
|
NEC ECC: W2 dispute resolution - period to notify
|
|
1
|
703
|
8 June 2020
|
NEC ECC: Retention on contracts
|
|
1
|
948
|
6 May 2020
|
NEC ECC: ECI - Additional clause for use with the NEC3 Engineering and Construction Contract (ECC)
|
|
1
|
567
|
16 April 2020
|
NEC TSC: Frequency of Price Adjustments for Inflation when using NEC4 TSC + X19
|
|
2
|
733
|
3 April 2020
|
NEC ECC: Notification associated with X2
|
|
3
|
1351
|
3 April 2020
|
NEC ECC: Amendment to secondary clause wording such as X22
|
|
3
|
900
|
27 March 2020
|
NEC ECC: What happens if Project Manager is beyond time to assess a quotation?
|
|
1
|
698
|
28 February 2020
|
NEC ECC: Use of collateral warranties or instead yuk3?
|
|
1
|
907
|
28 February 2020
|
NEC ECC: X18 - Indirect or Consequential Losses - What is a suitable level to cap this at?
|
|
1
|
2207
|
12 February 2020
|
NEC ECC: Missed KPI - What happens to the incentive payment?
|
|
1
|
1143
|
17 January 2020
|
NEC ECC: Does late issue of drawing amount to a compensation event .
|
|
1
|
982
|
10 January 2020
|
NEC ECC: X12 Partnering
|
|
1
|
622
|
2 January 2020
|
NEC TSC: Option A with option X19 - Instruction changing a Task Order
|
|
1
|
807
|
6 December 2019
|
NEC3 ECC Option X7
|
|
1
|
754
|
6 December 2019
|
NEC ECC: X7 - Levying of Delay Damages
|
|
1
|
737
|
6 December 2019
|
NEC TSC: Under option A, Option X1 - Adjustment Calculation for inflation
|
|
1
|
708
|
28 November 2019
|
NEC TSC: Defined Cost based on current rates adjusted to base date level
|
|
2
|
757
|
21 November 2019
|
NEC ECC: X16 Retention Clause
|
|
1
|
2976
|
14 November 2019
|
NEC ECC - what are the correct procedures for the Employer to claim under Clause X18 from the Contractor
|
|
1
|
1408
|
1 October 2019
|
NEC TSC - How does X1 adjustment for inflation work with CE's?
|
|
1
|
3350
|
24 September 2019
|
NEC ECC: Is the Contractor able to refer to a dispute?
|
|
3
|
1047
|
19 August 2019
|
NEC3 ECC: X7 Delay Damages on NEC3 Option E contract
|
|
2
|
982
|
19 August 2019
|
NEC3 ECS: Damages to be levied
|
|
1
|
567
|
16 August 2019
|