X1 PAF calculations

Hi,

I am trying to work out the PAF according to the contract condition as follows:
The proportion used to calculate the Price Adjustment Factor are
0. 20 linked to the index for 4/CE/EL/01 Electrical Engineering Labour
0. 15 linked to the index for 4/CE/EL/02 Electrical Engineering Materials
0. 20 linked to the index for 4/CE/ME/01 Mechanical Engineering Labour
0. 15 linked to the index for 4/CE/ME/02 Mechanical Engineering Materials
0. 10 linked to the index for 4/CE/01 Civil Engineering Labour
0. 10 linked to the index for 4/CE/02 Management and Administration
0. 10 non-adjustable

I have managed to work out the following:

Capture

i am not sure however how to calculate the factor for non adjustable 10% - do i keep the base rate at 100 and the current month indexation rate at 100? any help would be appreciated.

1 Like

Assuming this is an ECC form, the calculation should be (L-B)/B. B is the Base Date Index, so Jan 2020 in your case and L is the Latest Index, so is June 2021. This calculation is applied to each of the indices and then multiplied by the relevant proportion, as follows;

4/CE/EL/01 (115.8-115.2)/115.2 x 0.20 = 0.10%
4/CE/EL/02 (111.5-105.4)/105.4 x 0.15 = 0.87%
4/CE/ME/01 (114.2-113.9)/113.9 x 0.20 = 0.05%
4/CE/ME/02 (125.1-113.1)/113.1 x 0.15 = 1.59%
etc

The ‘products’ (resulting percentages) are added together to give the Price Adjustment Factor. In your case this totals 2.73%.

The ‘non-adjustable’ element would have an index of 100 which would never change so this would always equate to 0.00%, which means that 10% of the PWDD would not be adjusted.

How the PAF is applied depends on what main option you have.

1 Like

Thank you Andrew, this actually agrees with my calcs

image001.jpg

2 Likes