NEC4 - Termination of sub contract by sub contractor
|
|
1
|
1051
|
27 April 2021
|
NEC ECC: Under Option C are agency staff considered as Subcontractor or People Cost, when considering the application of the working area overhead?
|
|
4
|
1893
|
21 April 2021
|
NEC3 Option A - Access Dates/Prelims Reduction
|
|
7
|
1417
|
8 April 2021
|
NEC 3 Option E Deduction of cost based upon initial budget
|
|
2
|
1527
|
4 February 2021
|
Staff costs for a quotation not requested by the Project Manager
|
|
3
|
617
|
2 February 2021
|
NEC3 ECS Option B - Contra charges
|
|
1
|
1129
|
15 January 2021
|
NEC4 PSC Correct a payment certificate
|
|
1
|
1196
|
14 January 2021
|
NEC4 Non Payment
|
|
3
|
920
|
21 December 2020
|
NEC4 ECC Option C - PWDD definition includes for 'advance payments' based on forecasts?
|
|
3
|
4278
|
9 December 2020
|
Breach of Contract - Option C Defined Cost
|
|
2
|
529
|
24 November 2020
|
NEC3 ECC Option A: Late Payment Certificate & Late Payment
|
|
1
|
3175
|
14 October 2020
|
Payment under the NEC Supply Contract
|
|
1
|
813
|
3 October 2020
|
Disallowed Subcontractor Costs as the PM has not Accepted the Subcontractor under 26.3
|
|
3
|
1220
|
25 September 2020
|
NEC ECS Subcontractor failed to meet application date
|
|
1
|
876
|
8 September 2020
|
NEC4 option C and disallowing actual costs that are not substantiated
|
|
1
|
1307
|
3 September 2020
|
NEC ECS: Interest charges on subcontract payments
|
|
2
|
636
|
30 August 2020
|
NEC3 ECSC Short-Form - Payment Provisions
|
|
4
|
1078
|
28 August 2020
|
NEC ECC: Under Clause 50.1 of the NEC3 ECC Contract does the assessment interval start again once the assessment required at Completion is made or is the assessment at Completion in addition to the regular assessments made at the contractual assessment in
|
|
2
|
2832
|
24 August 2020
|
Payment for defective work
|
|
1
|
1052
|
12 August 2020
|
ECC NEC Option A - Payment on Termination
|
|
1
|
530
|
7 August 2020
|
NEC ECC: Is the Project Manager to certify two amounts due if there are multiple currencies
|
|
3
|
644
|
21 July 2020
|
NEC ECC: Employer activity schedule
|
|
1
|
1238
|
1 July 2020
|
NEC ECC: Mistake on employers Activity Schedule.
|
|
2
|
666
|
30 June 2020
|
NEC ECSS: Short sub contract payment
|
|
1
|
563
|
22 June 2020
|
NEC4 TSC: Option C - defined cost for staff before the actual start day of the task
|
|
2
|
614
|
18 June 2020
|
NEC ECS: Under NEC3 option A contract, can an appointed subcontractor use the money gained from selling unused scrap on other works in the project?
|
|
1
|
985
|
17 June 2020
|
NEC PSC: Under option C, what can change the Prices?
|
|
1
|
1079
|
12 June 2020
|
Activity Schedule accepted, but not the programme
|
|
1
|
806
|
8 June 2020
|
NEC ECS: Separate Activity for Management cost in an Option A Activity SChedule
|
|
1
|
678
|
3 June 2020
|
NEC ECC: Option A , Error in pricing - X15 is incorporated in the contract
|
|
5
|
1021
|
11 May 2020
|