NEC ECC: PM Default on Payment Notice
|
|
1
|
1594
|
26 February 2020
|
NEC ECC: Can the Contractor change the method that the pricing was based upon (and shown in the Accepted Programme)
|
|
5
|
930
|
13 February 2020
|
NEC ECC: What are the Application and payment timescales in the NEC4 Short Contract (ECSC)?
|
|
1
|
1943
|
9 February 2020
|
NEC ECC: Clause regarding the calculation of the monthly payment by the Project Manager?
|
|
1
|
468
|
29 January 2020
|
NEC ECC: Option E - Forecast Period
|
|
1
|
1069
|
27 January 2020
|
NEC ECC: Defined cost People rates - Hours utilisation for differing clients
|
|
1
|
1414
|
27 January 2020
|
NEC ECC: Disallowed subcontractor costs for delays?
|
|
2
|
749
|
23 January 2020
|
NEC ECS: Option A (Subcontract) - Main Contractor refusing to pay the Labour Element of shifts as number of activuty/shift was reduced in number from 5 to 3 Activity shifts.
|
|
2
|
336
|
14 January 2020
|
NEC PSC: Payless Notice
|
|
1
|
579
|
12 January 2020
|
NEC ECC: Assessment for lack of Warranties
|
|
2
|
697
|
9 January 2020
|
NEC ECC: What are the procedures for assessing and making interim payments?
|
|
1
|
1026
|
3 January 2020
|
NEC ECC - Final Assessment
|
|
1
|
1039
|
6 December 2019
|
NEC3 ECC: Fees applied under ECI Stage One - Option C, WAO/H or People OH?
|
|
2
|
401
|
3 December 2019
|
NEC ECC: Contractor's Overhead
|
|
1
|
848
|
2 December 2019
|
NEC ECC: The sum paid is greater than the sum certified - is interest due?
|
|
1
|
483
|
15 November 2019
|
NEC ECC: Can the Project Manager issue a pay less notice in the form of a PMI
|
|
1
|
367
|
11 November 2019
|
NEC ECC: PWDD at Completion Option A
|
|
1
|
1288
|
8 November 2019
|
NEC ECS: Sub-contractor payment dates
|
|
2
|
770
|
5 November 2019
|
NEC ECS: Sub contractor payment dates under NEC Option A
|
|
1
|
712
|
4 November 2019
|
NEC ECC: Payless notices?
|
|
1
|
767
|
1 November 2019
|
NEC ECC: What should the Project Manager do in the absence of an application for payment from the Contractor?
|
|
1
|
1518
|
27 October 2019
|
NEC PSC: Can the Employer ask to see salary information as a back up to Time Charge?
|
|
1
|
552
|
22 October 2019
|
NEC ECC: Is the cost of PPE, personalised shirts and fleeces paid for under Option C Target cost
|
|
1
|
1051
|
17 October 2019
|
NEC PSC Option C Time Charge
|
|
2
|
743
|
11 October 2019
|
NEC ECC: Is damaged equipment a disallowed cost?
|
|
1
|
1474
|
19 September 2019
|
NEC ECC: Payment for Works Information Preliminary Deliverables
|
|
2
|
925
|
1 September 2019
|
NEC PSC: Expenses recovered through audit and actual costs?
|
|
1
|
939
|
27 August 2019
|
NEC ECC: Can risk be included and paid for in a CE?
|
|
1
|
852
|
23 August 2019
|
Is this legitimate cost under the contract and should it be paid?
|
|
4
|
1160
|
21 August 2019
|
NEC ECS: Agreed reduction for early payment
|
|
2
|
455
|
19 August 2019
|