ECC NEC Option A - Payment on Termination

Under an Option A, how is the payment on termination dealt with?

It depends on what grounds the termination has occurred. if you look at the Termination Table found in Clause 90.2 of NEC4 this sets out the various options. Have a look at that.

1 Like