Breach of Contract - Option C Defined Cost

If the Subcontractor is late in delivering their subcontract works (i.e Breach of Contract) and X7 has not been selected, is the Contractor able to withhold Defined cost payments under 50.2 3rd bullet?

Omar can you confirm which contract you are using.

NEC3 Option C - Target subcontract with activity schedule