|
Miscalculation in activity schedule
|
|
6
|
472
|
25 April 2023
|
|
NEC4 PSC Option C 11.2 (21) PSPD Query
|
|
0
|
415
|
23 April 2023
|
|
Advanced payment for material products not yet manufactured
|
|
3
|
660
|
17 April 2023
|
|
NEC ECC - Option C, Title for materials where payment due during payment period (particularly during Corona Virus period)
|
|
4
|
1854
|
13 April 2023
|
|
NEC - Schedule of rates and fee %
|
|
3
|
1325
|
6 April 2023
|
|
NEC3 Option C: Changing a Subcontractor
|
|
1
|
426
|
15 March 2023
|
|
Payment of prelims under NEC3 option B
|
|
1
|
1055
|
5 March 2023
|
|
NEC4 Term Service Subcontract Option C
|
|
1
|
370
|
17 February 2023
|
|
NEC4 Option C Advance Works
|
|
2
|
429
|
28 January 2023
|
|
NEC3 ECC - Purchase of Plant or equipment - Residual Value
|
|
3
|
1072
|
23 January 2023
|
|
NEC3 Option C: Non Working Equipment on Site
|
|
4
|
552
|
16 January 2023
|
|
NEC ECC: What is "the amount of payments due to Subcontractors"?
|
|
2
|
1220
|
11 January 2023
|
|
NEC 4 Option B - Recovery for fabricated steel off site
|
|
3
|
560
|
16 December 2022
|
|
Advance Payments on the Payment Certificate
|
|
1
|
589
|
23 November 2022
|
|
NEC 4 Schedule of Cost Components and IT costs
|
|
1
|
1683
|
19 July 2022
|
|
NEC4 Clause 50.4 If the Contractor does not submit an application
|
|
0
|
1688
|
5 July 2022
|
|
ECC3 Pain/Gain Share Calculation
|
|
2
|
1001
|
14 June 2022
|
|
NEC3 Professional Services Contract- Application for Payment or Invoice?
|
|
3
|
969
|
20 May 2022
|
|
NEC Option A - An ambiguity between Works Information and Activity Schedule (contract documents)
|
|
1
|
621
|
28 February 2022
|
|
NEC3 Subcontract Option A Clause 63.5
|
|
4
|
655
|
7 February 2022
|
|
Interim Deduction of Delay Damages
|
|
1
|
618
|
4 February 2022
|
|
No response to PA from contractor by the due date
|
|
1
|
411
|
27 January 2022
|
|
Clause X16 - Take over and its impact on retention
|
|
1
|
1130
|
21 January 2022
|
|
NEC4 Option 4 - Missing Fee Percentage in Contract Data part two
|
|
3
|
4954
|
27 November 2021
|
|
Default Payment Notice under NEC 4 Subcontract
|
|
7
|
1767
|
9 November 2021
|
|
NEC3 ECC option A - change in activity schedule
|
|
2
|
5382
|
8 November 2021
|
|
NEC3 Option B - Client removing a BoQ item
|
|
3
|
504
|
8 November 2021
|
|
NEC Option C - Level of Cost Substantiation
|
|
1
|
821
|
2 November 2021
|
|
NEC Option E Defined Cost
|
|
0
|
537
|
27 October 2021
|
|
NEC4 Option C - Gain Share - Payment
|
|
2
|
650
|
27 August 2021
|