NEC4 Term Service Subcontract Option C
|
|
1
|
358
|
17 February 2023
|
NEC4 Option C Advance Works
|
|
2
|
416
|
28 January 2023
|
NEC3 ECC - Purchase of Plant or equipment - Residual Value
|
|
3
|
1017
|
23 January 2023
|
NEC3 Option C: Non Working Equipment on Site
|
|
4
|
476
|
16 January 2023
|
NEC ECC: What is "the amount of payments due to Subcontractors"?
|
|
2
|
1154
|
11 January 2023
|
NEC 4 Option B - Recovery for fabricated steel off site
|
|
3
|
544
|
16 December 2022
|
Advance Payments on the Payment Certificate
|
|
1
|
545
|
23 November 2022
|
NEC 4 Schedule of Cost Components and IT costs
|
|
1
|
1459
|
19 July 2022
|
NEC4 Clause 50.4 If the Contractor does not submit an application
|
|
0
|
1485
|
5 July 2022
|
ECC3 Pain/Gain Share Calculation
|
|
2
|
909
|
14 June 2022
|
NEC3 Professional Services Contract- Application for Payment or Invoice?
|
|
3
|
900
|
20 May 2022
|
NEC Option A - An ambiguity between Works Information and Activity Schedule (contract documents)
|
|
1
|
617
|
28 February 2022
|
NEC3 Subcontract Option A Clause 63.5
|
|
4
|
651
|
7 February 2022
|
Interim Deduction of Delay Damages
|
|
1
|
603
|
4 February 2022
|
No response to PA from contractor by the due date
|
|
1
|
394
|
27 January 2022
|
Clause X16 - Take over and its impact on retention
|
|
1
|
1029
|
21 January 2022
|
NEC4 Option 4 - Missing Fee Percentage in Contract Data part two
|
|
3
|
4753
|
27 November 2021
|
Default Payment Notice under NEC 4 Subcontract
|
|
7
|
1630
|
9 November 2021
|
NEC3 ECC option A - change in activity schedule
|
|
2
|
5271
|
8 November 2021
|
NEC3 Option B - Client removing a BoQ item
|
|
3
|
495
|
8 November 2021
|
NEC Option C - Level of Cost Substantiation
|
|
1
|
753
|
2 November 2021
|
NEC Option E Defined Cost
|
|
0
|
513
|
27 October 2021
|
NEC4 Option C - Gain Share - Payment
|
|
2
|
573
|
27 August 2021
|
Adjustment of Target (total of the prices) after Adjudication NEC3 ECC Option C
|
|
3
|
439
|
5 August 2021
|
Withholding Payments
|
|
1
|
686
|
2 August 2021
|
Cleaning Equipment Following a Change to the WI
|
|
1
|
473
|
19 July 2021
|
NEC 4 Option C - missed application for payment
|
|
1
|
543
|
30 June 2021
|
NEC3 Option C Insurance Premium Cost Recovery
|
|
2
|
1103
|
19 May 2021
|
NEC4 - Termination of sub contract by sub contractor
|
|
1
|
1026
|
27 April 2021
|
NEC ECC: Under Option C are agency staff considered as Subcontractor or People Cost, when considering the application of the working area overhead?
|
|
4
|
1850
|
21 April 2021
|