|
NEC4 clause 51.1 & 51.2 late payment
|
|
1
|
944
|
6 June 2023
|
|
NEC ECC: Under option C, are the costs of dealing with an adjudication brought by a subcontractor disallowed?
|
|
3
|
1925
|
1 June 2023
|
|
Advanced Payment on Subcontract Order
|
|
5
|
579
|
11 May 2023
|
|
Miscalculation in activity schedule
|
|
6
|
483
|
25 April 2023
|
|
NEC4 PSC Option C 11.2 (21) PSPD Query
|
|
0
|
420
|
23 April 2023
|
|
Advanced payment for material products not yet manufactured
|
|
3
|
694
|
17 April 2023
|
|
NEC ECC - Option C, Title for materials where payment due during payment period (particularly during Corona Virus period)
|
|
4
|
1879
|
13 April 2023
|
|
NEC - Schedule of rates and fee %
|
|
3
|
1389
|
6 April 2023
|
|
NEC3 Option C: Changing a Subcontractor
|
|
1
|
437
|
15 March 2023
|
|
Payment of prelims under NEC3 option B
|
|
1
|
1088
|
5 March 2023
|
|
NEC4 Term Service Subcontract Option C
|
|
1
|
379
|
17 February 2023
|
|
NEC4 Option C Advance Works
|
|
2
|
429
|
28 January 2023
|
|
NEC3 ECC - Purchase of Plant or equipment - Residual Value
|
|
3
|
1100
|
23 January 2023
|
|
NEC3 Option C: Non Working Equipment on Site
|
|
4
|
586
|
16 January 2023
|
|
NEC ECC: What is "the amount of payments due to Subcontractors"?
|
|
2
|
1254
|
11 January 2023
|
|
NEC 4 Option B - Recovery for fabricated steel off site
|
|
3
|
570
|
16 December 2022
|
|
Advance Payments on the Payment Certificate
|
|
1
|
609
|
23 November 2022
|
|
NEC 4 Schedule of Cost Components and IT costs
|
|
1
|
1752
|
19 July 2022
|
|
NEC4 Clause 50.4 If the Contractor does not submit an application
|
|
0
|
1768
|
5 July 2022
|
|
ECC3 Pain/Gain Share Calculation
|
|
2
|
1021
|
14 June 2022
|
|
NEC3 Professional Services Contract- Application for Payment or Invoice?
|
|
3
|
994
|
20 May 2022
|
|
NEC Option A - An ambiguity between Works Information and Activity Schedule (contract documents)
|
|
1
|
622
|
28 February 2022
|
|
NEC3 Subcontract Option A Clause 63.5
|
|
4
|
661
|
7 February 2022
|
|
Interim Deduction of Delay Damages
|
|
1
|
621
|
4 February 2022
|
|
No response to PA from contractor by the due date
|
|
1
|
413
|
27 January 2022
|
|
Clause X16 - Take over and its impact on retention
|
|
1
|
1166
|
21 January 2022
|
|
NEC4 Option 4 - Missing Fee Percentage in Contract Data part two
|
|
3
|
5021
|
27 November 2021
|
|
Default Payment Notice under NEC 4 Subcontract
|
|
7
|
1813
|
9 November 2021
|
|
NEC3 ECC option A - change in activity schedule
|
|
2
|
5402
|
8 November 2021
|
|
NEC3 Option B - Client removing a BoQ item
|
|
3
|
513
|
8 November 2021
|