NEC - Schedule of rates and fee %
|
|
3
|
1269
|
6 April 2023
|
NEC3 Option C: Changing a Subcontractor
|
|
1
|
424
|
15 March 2023
|
Payment of prelims under NEC3 option B
|
|
1
|
1002
|
5 March 2023
|
NEC4 Term Service Subcontract Option C
|
|
1
|
368
|
17 February 2023
|
NEC4 Option C Advance Works
|
|
2
|
427
|
28 January 2023
|
NEC3 ECC - Purchase of Plant or equipment - Residual Value
|
|
3
|
1055
|
23 January 2023
|
NEC3 Option C: Non Working Equipment on Site
|
|
4
|
523
|
16 January 2023
|
NEC ECC: What is "the amount of payments due to Subcontractors"?
|
|
2
|
1194
|
11 January 2023
|
NEC 4 Option B - Recovery for fabricated steel off site
|
|
3
|
558
|
16 December 2022
|
Advance Payments on the Payment Certificate
|
|
1
|
571
|
23 November 2022
|
NEC 4 Schedule of Cost Components and IT costs
|
|
1
|
1593
|
19 July 2022
|
NEC4 Clause 50.4 If the Contractor does not submit an application
|
|
0
|
1621
|
5 July 2022
|
ECC3 Pain/Gain Share Calculation
|
|
2
|
964
|
14 June 2022
|
NEC3 Professional Services Contract- Application for Payment or Invoice?
|
|
3
|
934
|
20 May 2022
|
NEC Option A - An ambiguity between Works Information and Activity Schedule (contract documents)
|
|
1
|
619
|
28 February 2022
|
NEC3 Subcontract Option A Clause 63.5
|
|
4
|
652
|
7 February 2022
|
Interim Deduction of Delay Damages
|
|
1
|
613
|
4 February 2022
|
No response to PA from contractor by the due date
|
|
1
|
407
|
27 January 2022
|
Clause X16 - Take over and its impact on retention
|
|
1
|
1091
|
21 January 2022
|
NEC4 Option 4 - Missing Fee Percentage in Contract Data part two
|
|
3
|
4876
|
27 November 2021
|
Default Payment Notice under NEC 4 Subcontract
|
|
7
|
1691
|
9 November 2021
|
NEC3 ECC option A - change in activity schedule
|
|
2
|
5354
|
8 November 2021
|
NEC3 Option B - Client removing a BoQ item
|
|
3
|
504
|
8 November 2021
|
NEC Option C - Level of Cost Substantiation
|
|
1
|
800
|
2 November 2021
|
NEC Option E Defined Cost
|
|
0
|
532
|
27 October 2021
|
NEC4 Option C - Gain Share - Payment
|
|
2
|
615
|
27 August 2021
|
Adjustment of Target (total of the prices) after Adjudication NEC3 ECC Option C
|
|
3
|
446
|
5 August 2021
|
Withholding Payments
|
|
1
|
693
|
2 August 2021
|
Cleaning Equipment Following a Change to the WI
|
|
1
|
475
|
19 July 2021
|
NEC 4 Option C - missed application for payment
|
|
1
|
567
|
30 June 2021
|