NEC4 ECC: Appendix 5 Example tender assessment sheet
|
|
2
|
1916
|
27 September 2019
|
|
NEC ECC: Does the period for reply apply to the Contractor as well
|
|
6
|
3218
|
11 September 2019
|
|
NEC ECS: What is the purpose of naming the Employer/Client and Project Manager in CD1?
|
|
1
|
597
|
5 August 2019
|
|
NEC ECC: Contract Data Part 2 - How do we respond with more than a Single Fee
|
|
2
|
2081
|
25 July 2019
|
|
NEC ECS: Additional terms associated with key people
|
|
2
|
1338
|
24 July 2019
|
|
NEC ECC: If the Project Manager accepts a Project programme and the Planned Dates are later than the Contract Dates what is the client accepting?
|
|
2
|
749
|
16 July 2019
|
|
NEC ECS: Option b subcontract %
|
|
2
|
563
|
16 July 2019
|
|
NEC ECC: Option A correct fee % application
|
|
1
|
623
|
11 July 2019
|
|
NEC ECC: Planned Completion being driven by a third party
|
|
2
|
1053
|
26 June 2019
|
|
NEC ECC: Provision of equipment an Employers Risk or Contractors?
|
|
1
|
420
|
20 June 2019
|
|
NEC3 ECC, Assessment on delay to Activities - Option A
|
|
1
|
586
|
17 June 2019
|
|
NEC ECC: Can the contractors share ranges be changed after contract award
|
|
2
|
442
|
11 June 2019
|
|
NEC ECC: Imposing Sectional Delay Damages
|
|
10
|
2686
|
6 June 2019
|
|
NEC ECS: Works Information referred to in Contract Data - Conflict
|
|
2
|
901
|
13 May 2019
|
|
NEC4 ECC - inconsistency between Contract Data and a Z Clause
|
|
6
|
845
|
25 April 2019
|
|
NEC ECC: Key Person change
|
|
1
|
2472
|
15 April 2019
|
|
NEC ECC: Removal of completion criteria for Key Date
|
|
1
|
578
|
4 April 2019
|
|
NEC ECC - Referencing other documents from Contract Data Part One
|
|
3
|
1051
|
2 April 2019
|
|
NEC ECC: Does the Project Manager have to be a named individual?
|
|
1
|
1531
|
14 March 2019
|
|
NEC ECC: Are durations of Employer’s activities shown in the Contractor 1st Programme for Acceptance submitted as part of Contract Data Part 2 considered as Agreed, and supersede durations stated in the Works Information?
|
|
8
|
1358
|
5 March 2019
|
|
Under the NEC Contract option A, when do you apply the direct fee % and the Subcontracted fee percentage?
|
|
7
|
31064
|
4 March 2019
|
|
NEC4 PSS - Subcontract Data - why no Site Information?
|
|
1
|
612
|
7 February 2019
|
|
NEC ECC: Honeymoon period from damages?
|
|
4
|
571
|
29 January 2019
|
|
NEC ECC: People overhead inconsistency
|
|
2
|
750
|
9 January 2019
|
|
NEC ECC: Direct Fee or Subcontract Fee Option A/B
|
|
3
|
3319
|
16 November 2018
|
|
NEC ECS: calculating payment with blank contract data on termination
|
|
1
|
483
|
13 November 2018
|
|
NEC ECS: Option A - Completion Date with long lead manufacturing
|
|
2
|
575
|
8 November 2018
|
|
NEC ECC: Dates in Contract Data vs Programme
|
|
2
|
1734
|
30 October 2018
|
|
NEC ECC: Works Information and Price List.
|
|
1
|
622
|
30 September 2018
|
|
NEC ECC: Option B (further question) what is remeasured?
|
|
2
|
1989
|
28 September 2018
|