NEC ECC: Imposing Sectional Delay Damages
|
|
10
|
697
|
6 June 2019
|
NEC ECS: Works Information referred to in Contract Data - Conflict
|
|
2
|
441
|
13 May 2019
|
NEC4 ECC - inconsistency between Contract Data and a Z Clause
|
|
6
|
378
|
25 April 2019
|
NEC ECC: Key Person change
|
|
1
|
618
|
15 April 2019
|
NEC ECC: Removal of completion criteria for Key Date
|
|
1
|
181
|
4 April 2019
|
NEC ECC - Referencing other documents from Contract Data Part One
|
|
3
|
245
|
2 April 2019
|
NEC ECC: Does the Project Manager have to be a named individual?
|
|
1
|
386
|
14 March 2019
|
NEC ECC: What items should be included / allowed for when calculating percentage for peoples overheads?
|
|
1
|
1083
|
6 March 2019
|
NEC ECC: Are durations of Employer’s activities shown in the Contractor 1st Programme for Acceptance submitted as part of Contract Data Part 2 considered as Agreed, and supersede durations stated in the Works Information?
|
|
8
|
397
|
5 March 2019
|
Under the NEC Contract option A, when do you apply the direct fee % and the Subcontracted fee percentage?
|
|
7
|
26121
|
4 March 2019
|
NEC4 PSS - Subcontract Data - why no Site Information?
|
|
1
|
164
|
7 February 2019
|
NEC ECC: Honeymoon period from damages?
|
|
4
|
198
|
29 January 2019
|
NEC ECC: People overhead inconsistency
|
|
2
|
374
|
9 January 2019
|
NEC ECC: Direct Fee or Subcontract Fee Option A/B
|
|
3
|
1214
|
16 November 2018
|
NEC ECS: calculating payment with blank contract data on termination
|
|
1
|
148
|
13 November 2018
|
NEC ECS: Option A - Completion Date with long lead manufacturing
|
|
2
|
254
|
8 November 2018
|
NEC ECC: Dates in Contract Data vs Programme
|
|
2
|
627
|
30 October 2018
|
NEC ECC: Works Information and Price List.
|
|
1
|
244
|
30 September 2018
|
NEC ECC: Option B (further question) what is remeasured?
|
|
2
|
415
|
28 September 2018
|
NEC ECC: Option C Contract - Pain/Gain Range and Percentage Blank
|
|
4
|
892
|
28 September 2018
|
NEC ECSC: Deletion of item from Price List
|
|
1
|
224
|
21 September 2018
|
NEC ECC: Under NEC3 Option A, what must be covered by the sub-contractor fee?
|
|
5
|
924
|
19 September 2018
|
NEC ECC: Subcontracted Fee for ECC Option C
|
|
1
|
189
|
4 August 2018
|
NEC ECC: Option A - Cancellation Fees
|
|
4
|
1031
|
19 April 2018
|
NEC FC: Framework Contract, what takes precedence?
|
|
1
|
363
|
19 April 2018
|
NEC ECC: Apply subcontractor fee on group company?
|
|
3
|
518
|
31 January 2018
|
NEC ECC: Direct fee and subcontract fee on NEC3 ECC option E contract
|
|
1
|
940
|
24 November 2017
|
NEC ECC: No Sub-Contract Fee Stated in the Contract Data
|
|
1
|
300
|
11 November 2017
|
NEC3 ECC: Applying Working & Design Area Overheads
|
|
1
|
561
|
25 July 2017
|
NEC3 ECC: Option E - Working & Design Area Overheads
|
|
3
|
911
|
25 July 2017
|