The Contractor on site has a 10 week programme is ahead by 2 weeks, despite also completing a number of variations which have caused a 2 week delay to the critical path.
Is the Contractor entitled to 8, 10, or 12 weeks prelims?
They are arguing they are entitled to 12 as they should get the benefit of being ahead by out performing their productions and working over time.