Zero value compensation events....?
|
|
3
|
338
|
22 December 2023
|
NEC 3 - Quotations for Compensation Events
|
|
2
|
426
|
15 December 2023
|
ECC Option A for new car park
|
|
5
|
298
|
7 December 2023
|
NEC4 Type A - PM Omitting Costs
|
|
1
|
188
|
5 December 2023
|
Equipment Rates
|
|
1
|
170
|
5 December 2023
|
NEC4 ECC : Searching for similar defects - Is it a CE?
|
|
1
|
165
|
4 December 2023
|
NEC3 - ECS - Option B - Clause 60.7
|
|
1
|
248
|
28 November 2023
|
Can an NEC3 Programme accepted too early avoid full assessment of a compensation event?
|
|
7
|
397
|
23 November 2023
|
Which type of compensation event is applicable to the following situation?
|
|
2
|
207
|
20 November 2023
|
CE impact on planned completion ahead of contract completion (NEC4 - Option C)
|
|
1
|
449
|
17 November 2023
|
NEC4 ECSC - Defined Cost of People preparing quotation
|
|
3
|
481
|
12 November 2023
|
NEC 4 ECS Option A - CE Quotation as a CE Notification
|
|
4
|
223
|
10 November 2023
|
Compensation Events Time Only
|
|
1
|
455
|
10 November 2023
|
NEC4: Developing quotation time
|
|
1
|
181
|
9 November 2023
|
Negative Compensation Event
|
|
0
|
513
|
28 September 2021
|
NEC4 Short Subcontract Negative CE
|
|
0
|
498
|
8 January 2022
|
Cl 63.1 in NEC3 OpA Supply
|
|
0
|
275
|
1 June 2023
|
NEC 4 Option B - Late assessment of Compensation Event and Impact to Interim Payment
|
|
0
|
308
|
27 June 2023
|
Bill items included in priced BoQ, but not included in Works Information
|
|
3
|
309
|
7 November 2023
|
Large Instructions to Subcontractor
|
|
5
|
608
|
1 November 2023
|
Is failure to comply with a constraint in the Works Information a Defect
|
|
1
|
402
|
1 November 2023
|
Multiple CEs under one instruction
|
|
0
|
450
|
9 June 2021
|
NEC3 TSC - PM changing the Works Information
|
|
0
|
178
|
26 October 2023
|
NEC3 - ECS - Plant Stand Down Costs due to Prevention of Access
|
|
1
|
226
|
23 October 2023
|
NEC3 Option A - Inflation Calculation no X1
|
|
1
|
204
|
20 October 2023
|
NEC ECS: Under an option A Contract, is an agreed schedule of labour rates in the Works Information valid for assessing CE's?
|
|
4
|
4090
|
19 October 2023
|
NEC4 Option B - application of credits for reduced/ omitted work after Completion
|
|
1
|
487
|
19 October 2023
|
Pricing Risk Under Clause 63.6
|
|
1
|
712
|
19 October 2023
|
Contractor Claim for CE for conflicting information
|
|
1
|
514
|
19 October 2023
|
Credit Value for Equipment
|
|
1
|
366
|
19 October 2023
|