Hi,
We are undertaking an option A NEC3 contract, whereby the Completion Date has been significantly delayed due to reasons outside of our control, although our works have been installed, and in use for some time by the end user (taken over under Clause 35).
We are obliged under the NEC3 contract to provide defect liability cover up to the Defects Date (70 weeks after Completion). Since our Plant and Materials have been installed on time, but the Defect Date has now moved considerably to the right, are we entitled to cover the risk associated with an extended defects liability period within a Compensation Event under Clause 63.6?
Many thanks for any guidance received.