NEC 4 - Use of X20
|
|
1
|
449
|
11 April 2024
|
People in Compensation Event Quotations
|
|
1
|
179
|
10 April 2024
|
Corruption act. In NEC4
|
|
1
|
249
|
3 April 2024
|
Release Notes upto 2024-03-26 Academy
|
|
0
|
237
|
26 March 2024
|
NEC3 Option B Clause 60.6
|
|
1
|
411
|
25 March 2024
|
Reopening implemented Compensation Events
|
|
1
|
392
|
25 March 2024
|
NEC3, Option B - BQ Item and Omitted Item
|
|
1
|
319
|
25 March 2024
|
Cost deduction for defect that was not notified
|
|
2
|
299
|
23 March 2024
|
Payless Notice Requirements
|
|
5
|
485
|
19 March 2024
|
NEC3, Option C - Schedule of Cost Components
|
|
1
|
320
|
19 March 2024
|
Unimplemented CE's
|
|
2
|
455
|
18 March 2024
|
NEC 3, Option B
|
|
2
|
477
|
18 March 2024
|
NEC3 ECC: Can the quantities of a CE for Option B be remeasured?
|
|
4
|
3759
|
18 March 2024
|
NEC3 Option B - Clause 60.4
|
|
8
|
796
|
18 March 2024
|
NEC4 - Take-over Cl35.2 & Liabilities under Cl80.1
|
|
2
|
469
|
15 March 2024
|
NEC4 - CE to reduce scope
|
|
1
|
648
|
8 March 2024
|
NEC 4 Option E - Bespoke Fee clause
|
|
1
|
471
|
8 March 2024
|
Does the SSCC need to be comprehensive?
|
|
6
|
479
|
8 March 2024
|
Webinar - Consequences of failing to complete the works before the completion date and LADs under JCT D&B Contract
|
|
11
|
1787
|
6 March 2024
|
NEC 4 Option A - Extensive Change in the scope of works
|
|
5
|
626
|
6 March 2024
|
Release Notes upto 2024-02-28 Academy
|
|
0
|
368
|
28 February 2024
|
Programme implications of a PMI issued as a result of late design
|
|
1
|
341
|
27 February 2024
|
NEC3 Option E - Contractor use of vehicles/transportation
|
|
2
|
429
|
27 February 2024
|
Option C Deep excavation to the lighting columns
|
|
3
|
643
|
23 February 2024
|
CE's on Option A Contract
|
|
4
|
772
|
23 February 2024
|
NEC3 Option A Subcontract - Defined Costs: What should be included in the agreed hourly rate for a CE?
|
|
2
|
1250
|
23 February 2024
|
Compensation Events in Option A applications for payment
|
|
5
|
1555
|
23 February 2024
|
Increase in materials unit cost due to reduced Scope
|
|
3
|
535
|
23 February 2024
|
NEC3 ECC - Option B - Remeasurement Basis
|
|
5
|
1173
|
23 February 2024
|
Last Accepted Programme
|
|
2
|
548
|
23 February 2024
|