Welcome to ReachBack
|
|
1
|
2890
|
28 November 2021
|
Activity Schedule
|
|
1
|
16
|
23 April 2025
|
NEC 4 - Equipment
|
|
2
|
23
|
22 April 2025
|
Nec3 compensation for information delay
|
|
2
|
45
|
22 April 2025
|
Cost of Correction of Defects in a NEC 3 Option F
|
|
0
|
14
|
16 April 2025
|
Release Notes up to 2025-04-14 Contract Management Sprint 113
|
|
0
|
10
|
15 April 2025
|
NEC3 - Correcting a PM Assumption
|
|
2
|
34
|
13 April 2025
|
NEC4 Option C - X1 & X2, Increase in employers national insurance contributions
|
|
2
|
91
|
10 April 2025
|
Defect in an NEC Option A subcontractors works
|
|
3
|
34
|
9 April 2025
|
NEC3 Lack of Access CE
|
|
5
|
145
|
9 April 2025
|
NEC4 TSC contracts
|
|
2
|
20
|
2 April 2025
|
Contract Date & Start Date - NEC 3
|
|
3
|
35
|
1 April 2025
|
Release Notes up to 2025-03-29 Contract Management Sprint 112
|
|
0
|
9
|
31 March 2025
|
NEC Term Service Agreement Option A - Prelims
|
|
0
|
16
|
31 March 2025
|
Release Notes upto 2025-03-31 Academy
|
|
0
|
12
|
31 March 2025
|
Inconsistency or Ambiguity in Works Information
|
|
1
|
50
|
31 March 2025
|
Failure of a Contractor to follow the NEC 4 rules particularly regarding CE assessment
|
|
3
|
56
|
28 March 2025
|
EWNs on facility for supply of goods - what is the client´s limit?
|
|
0
|
13
|
28 March 2025
|
Percentage for adjustment for Equipment in the published list
|
|
2
|
53
|
27 March 2025
|
How to certify payment when an advanced payment bond is required
|
|
2
|
31
|
27 March 2025
|
Inclusion of 'Unimplemented' CE in Forecast and Assessment
|
|
1
|
51
|
25 March 2025
|
NEC4 Option A Compensation Event
|
|
1
|
38
|
25 March 2025
|
Can the PD be instructed to use your (PC) programme dates by the client?
|
|
0
|
17
|
24 March 2025
|
NEC3 ECC Subcontract - De-Scoping the Works Information (costs in relation to)
|
|
0
|
37
|
24 March 2025
|
NEC3 EC Short Contract - Communcations and Period of Reply
|
|
1
|
24
|
19 March 2025
|
NEC4 PSC - Changes to People Rates under SSoCC
|
|
5
|
71
|
19 March 2025
|
Delegating Clauses 10 & 13
|
|
1
|
30
|
18 March 2025
|
NEC 4, Option A - The accepted programme
|
|
7
|
1044
|
18 March 2025
|
Notice of delay, potential claim for L&E, statutory undertakers, JCT DB 16
|
|
0
|
22
|
18 March 2025
|
Release Notes up to 2025-03-15 Contract Management Sprint 111
|
|
0
|
9
|
17 March 2025
|