Hello - A question regarding the remeasure on an Option B.
Assuming the original Bill of Quantities stated:
Item Quantity Rate
C20 Concrete 10m3 £150/m3
In a scenario where the Contractor ended up pouring 15m3, they would have been paid according to the bill rate up to the point the line item was completed i.e. £2,250. Assuming they notify a Compensation Event correctly under Cl60.4, would the remeasure apply only to the extra over (Cl.60.4 references "a different between the final quantity of work and the quantity stated in the bill) in this case the 5m3 ? Assuming the unit rate for the additional 5m3 increased to £200/m3, the CE quote is effectively £250 (having already been paid the bill rate of £150m3 for the extra over 5m3). Would this be the correct remeasure CE quotation provided by the Contractor ?
In addition, assuming the final quantity is significantly less than the stated amount in the bill, can the PM notify a Compensation Event (assuming the lower quantity lowered the unit rate stated in the bill, for example if the Contractor were able to cancel the remaining order and save on transport cost, thereby reducing the overall unit rate) ? Assuming the Contractor is unlikely to notify in this scenario as it reduces their potential profit margin.