I am using NEC ECC Option A and wish to insert a termination clause that will enable me as the Contractor to terminate should the client not provide me with a minimum number of jobs as falling below this number would put me in a loss situation?
It isn’t possible for the Client to use Option A of the ECC without specifying and describing the works in their entirety, it isn’t intended to be used as a call-off contract and would need significant amendment to make it work in the way you describe.
It would be better to use either the TSC (term service contract) or TSSC (term service short contract).