NEC ECS: Clause 90.3 intention to terminate contract
|
|
3
|
2419
|
6 November 2018
|
NEC ECC: Can someone describe the process the Employer will do in termination P1 & P2
|
|
1
|
1286
|
29 October 2018
|
NEC ECC: Roles in termination
|
|
1
|
1280
|
17 October 2018
|
NEC ECC: Employer Notified Termination Under Reason 90.3 R3
|
|
1
|
668
|
12 September 2018
|
NEC ECC: Employer termination and managing defects
|
|
1
|
1568
|
30 August 2018
|
NEC ECC: Does termination of the main contract by an Employer for a reason other than R1-R21 amount to prevention as a reason for the Contractor to terminate a Subcontract under NEC3
|
|
1
|
1265
|
22 August 2018
|
NEC ECC: Clarification of question on termination and liability for defects?
|
|
1
|
853
|
2 July 2018
|
NEC ECC: Payments on termination
|
|
1
|
1902
|
30 May 2018
|
NEC ECC: If the Contractor terminates the contract under reason R16 what are the obligations of the Contractor to the Employer with regard to the defects liability period
|
|
1
|
737
|
27 April 2018
|
NEC TSC: What are the implications of an Employer's common law repudiation of Contract?
|
|
1
|
1208
|
20 April 2018
|
NEC TSC: The Employer has 'defined' R11 under a service level table , but will it meet the legal test for substantial failure
|
|
3
|
784
|
13 April 2018
|
NEC TSC: Does the wording of Clause 90.2 exclude common law termination?
|
|
3
|
1158
|
13 April 2018
|
NEC TSC: Are the provisions of Clause 91.2 dependent on following the procedure as listed under Clause 90.1 or can termination be effected directly
|
|
2
|
1158
|
11 April 2018
|
NEC ECS: Termination certificate - what should it look like and are we obliged to issue one?
|
|
2
|
2936
|
22 February 2018
|
NEC ECC: Should contractor Insolvency result to a breach of contract to the Employer?
|
|
2
|
1195
|
4 January 2018
|
NEC ECS: Wrongful termination by the Contractor
|
|
1
|
659
|
22 November 2017
|
NEC3 ECC: Termination for convenience
|
|
2
|
3169
|
27 July 2017
|
NEC ECC: If the Employer wishes to terminate a contract due to lack of funds, is this classified as reason R21 or would it be classified as a reason other than R1-R21?
|
|
1
|
718
|
26 May 2017
|
NEC3 ECC: Can an Employer withhold monies for defective works from an assessment due once they have terminated for convenience?
|
|
1
|
894
|
24 March 2017
|
NEC3 ECC: Due date for terminated final payment
|
|
1
|
1328
|
24 March 2017
|
NEC3 ECC: Assessment periods after termination notified
|
|
1
|
1091
|
20 March 2017
|
NEC3 PSC: Can secondary Option Clause X11 be included in the NEC3 PSC when operating under Option E Cost reinbursable?
|
|
1
|
2635
|
17 March 2017
|
NEC3 TSC: Can an Employer insist on removal of a subcontractor under TSC if the subcontractor is not performing?
|
|
1
|
545
|
25 February 2017
|
NEC3 ECC: Is a direct fee percentage on the total contract sum due immediately if a contract is terminated for convenience by the Employer?
|
|
1
|
777
|
14 February 2017
|
NEC3 ECC: How long after termination does the Project Manager certify a final payment to or from the Contractor on Short Subcontract?
|
|
1
|
759
|
20 December 2016
|
NEC3 ECC: Termination but retain Subcontractors Equipment
|
|
1
|
667
|
7 November 2016
|
NEC3 ECC: The Employer has run out of money on an ECC Option A contract, Can he terminate without notice?
|
|
2
|
1091
|
4 September 2016
|
NEC3 ECC: What happens if the Employer has terminated the contract but does not instruct the Contractor to leave the Site, under P2?
|
|
1
|
1076
|
16 June 2016
|
NEC3 ECC: Does the notification of a defect automatically require a response without specifically asking for one?
|
|
2
|
2802
|
19 February 2016
|
NEC3 Short contract termination
|
|
1
|
1833
|
25 January 2016
|