Main contractor perspective, subcontractor is insolvent, currently on a default notice for significant hindrance (not placing orders for plant required) .
Has come to light subs are likely to become insolvent.
Question is, does the current default notice require amending, if no longer terminating for stated R14 reasons ? Or do we need to amend for R1 - R10 reasons ?
Or is it better to pursue original default (due to terminate in 2 weeks) rather than wait for a notice in the Gazette etc ?
Also if we know they are likely to become insolvent, can we reasonable appoint others to carry out their works if no longer on site before the date for termination.
Thanks