Is this legitimate cost under the contract and should it be paid?
|
|
4
|
1176
|
21 August 2019
|
NEC ECS: Agreed reduction for early payment
|
|
2
|
461
|
19 August 2019
|
NEC ECS: Not received signed option A subcontract
|
|
2
|
649
|
19 August 2019
|
NEC ECC: Option A - Interest due on Late Payment
|
|
1
|
1575
|
30 July 2019
|
NEC ECC: Payment of Defined Cost to the Next Assessment Date
|
|
1
|
1452
|
23 July 2019
|
NEC ECC: Can Contractor be paid for an item they have not been included on the activity schedule?
|
|
3
|
1296
|
22 July 2019
|
NEC ECS: Option B - Payment For Prolongation
|
|
1
|
576
|
22 July 2019
|
NEC ECS: Option B - Does PWDD include value of unimplemented Compensation Events?
|
|
1
|
502
|
10 July 2019
|
NEC ECC: Isn't 11.2(23) a double negative?
|
|
1
|
449
|
4 July 2019
|
NEC ECC: Can we claim for delivery of materials on site, if this is not listed as an activity on the activity schedule?
|
|
2
|
2033
|
4 July 2019
|
NEC ECC: Contractor Share arrangement
|
|
1
|
1193
|
4 July 2019
|
NEC ECC - Contractor on option E is in delay
|
|
3
|
1565
|
21 June 2019
|
NEC ECC: What can Contractor can do if the Payment Assessment by Project Manager is incorrect in previous month
|
|
1
|
1465
|
17 June 2019
|
NEC PSC: Should a forecast of expenses be included within the tendered Prices under option A?
|
|
1
|
467
|
17 June 2019
|
NEC ECC: How to calculate the Gain Sharing when Contractor Defects are involved
|
|
1
|
2089
|
14 June 2019
|
NEC ECC: Can PM designate certain brand of consumables in PM offices in an Option C contract?
|
|
2
|
1018
|
14 June 2019
|
NEC PSC: What relevance are Employer expenses in CD1?
|
|
3
|
525
|
14 June 2019
|
NEC ECC - Payment on consumables
|
|
2
|
3114
|
13 June 2019
|
NEC ECC - payment inspection
|
|
2
|
3413
|
10 June 2019
|
NEC ECC: BoQ items doubled up?
|
|
1
|
480
|
10 June 2019
|
NEC ECC: When is the assessment date?
|
|
1
|
3301
|
3 June 2019
|
NEC ECC: Option B:- Compensation Events and missing items
|
|
2
|
2093
|
23 May 2019
|
NEC4 ECC: Next Payment Date option C
|
|
1
|
1863
|
22 May 2019
|
NEC3 ECC Option C: Are professional subscriptions / memberships Defined Cost?
|
|
1
|
607
|
1 May 2019
|
NEC ECC: What is WAO applied to
|
|
1
|
1614
|
15 April 2019
|
NEC ECC: Claiming for prelims when contract period is extended?
|
|
1
|
1185
|
4 April 2019
|
NEC ECC: Payment for Deposit Charges
|
|
4
|
633
|
2 April 2019
|
NEC ECC: Can the client limit payment to agreed target value only on option C.
|
|
5
|
527
|
19 March 2019
|
NEC ECC: Specified material now on long lead time - is this a CE?
|
|
1
|
456
|
10 March 2019
|
NEC PSC: What is the risk to Consultants under option E for defects i.e. can costs be disallowed?
|
|
1
|
2826
|
8 March 2019
|