|
NEC3 ECC: Fees applied under ECI Stage One - Option C, WAO/H or People OH?
|
|
2
|
441
|
3 December 2019
|
|
NEC ECC: Contractor's Overhead
|
|
1
|
1043
|
2 December 2019
|
|
NEC ECC: The sum paid is greater than the sum certified - is interest due?
|
|
1
|
543
|
15 November 2019
|
|
NEC ECC: Can the Project Manager issue a pay less notice in the form of a PMI
|
|
1
|
456
|
11 November 2019
|
|
NEC ECC: PWDD at Completion Option A
|
|
1
|
1386
|
8 November 2019
|
|
NEC ECS: Sub-contractor payment dates
|
|
2
|
1033
|
5 November 2019
|
|
NEC ECS: Sub contractor payment dates under NEC Option A
|
|
1
|
801
|
4 November 2019
|
|
NEC ECC: Payless notices?
|
|
1
|
897
|
1 November 2019
|
|
NEC ECC: What should the Project Manager do in the absence of an application for payment from the Contractor?
|
|
1
|
1665
|
27 October 2019
|
|
NEC PSC: Can the Employer ask to see salary information as a back up to Time Charge?
|
|
1
|
631
|
22 October 2019
|
|
NEC ECC: Is the cost of PPE, personalised shirts and fleeces paid for under Option C Target cost
|
|
1
|
1263
|
17 October 2019
|
|
NEC PSC Option C Time Charge
|
|
2
|
802
|
11 October 2019
|
|
NEC ECC: Is damaged equipment a disallowed cost?
|
|
1
|
1761
|
19 September 2019
|
|
NEC ECC: Payment for Works Information Preliminary Deliverables
|
|
2
|
951
|
1 September 2019
|
|
NEC PSC: Expenses recovered through audit and actual costs?
|
|
1
|
1145
|
27 August 2019
|
|
NEC ECC: Can risk be included and paid for in a CE?
|
|
1
|
1223
|
23 August 2019
|
|
Is this legitimate cost under the contract and should it be paid?
|
|
4
|
1349
|
21 August 2019
|
|
NEC ECS: Agreed reduction for early payment
|
|
2
|
473
|
19 August 2019
|
|
NEC ECS: Not received signed option A subcontract
|
|
2
|
679
|
19 August 2019
|
|
NEC ECC: Option A - Interest due on Late Payment
|
|
1
|
1824
|
30 July 2019
|
|
NEC ECC: Payment of Defined Cost to the Next Assessment Date
|
|
1
|
1697
|
23 July 2019
|
|
NEC ECC: Can Contractor be paid for an item they have not been included on the activity schedule?
|
|
3
|
1456
|
22 July 2019
|
|
NEC ECS: Option B - Payment For Prolongation
|
|
1
|
649
|
22 July 2019
|
|
NEC ECS: Option B - Does PWDD include value of unimplemented Compensation Events?
|
|
1
|
576
|
10 July 2019
|
|
NEC ECC: Isn't 11.2(23) a double negative?
|
|
1
|
492
|
4 July 2019
|
|
NEC ECC: Can we claim for delivery of materials on site, if this is not listed as an activity on the activity schedule?
|
|
2
|
2613
|
4 July 2019
|
|
NEC ECC: Contractor Share arrangement
|
|
1
|
1355
|
4 July 2019
|
|
NEC ECC - Contractor on option E is in delay
|
|
3
|
1859
|
21 June 2019
|
|
NEC ECC: What can Contractor can do if the Payment Assessment by Project Manager is incorrect in previous month
|
|
1
|
1701
|
17 June 2019
|
|
NEC PSC: Should a forecast of expenses be included within the tendered Prices under option A?
|
|
1
|
532
|
17 June 2019
|