We are under contract with a Subcontractor on a two stage contract, using the NEC3 ECI addendum, Option C.
Stage One applications are being submitted by the Subcontractor applying People Overhead for People costs, and Direct Fee to People and other categories.
No target has yet been agreed (part of Stage One WI), and final ECI cost will form part of the eventual agreed target.
With this in mind, I am of the opinion that Working Area Overhead should be applied to People costs in Stage One applications, not People Overhead?
Any advice would be appreciated