Under clause X16 of our NEC4 ECC (Option C) contract it states retention of 5% of our defined cost is to be held until:
X16.1 – The earlier of either: Completion of the whole of the works, or the date on which the Client takes over the whole of the works. In this case the Contract Data states our Client is willing to take over the works.
Following this, under X16.2, half of the amount retained is released.
My query here is on the definition of ‘take over’.
The Client is a water company. We believe once the final connection has been completed and they have use of the new asset, they have taken it over and should release half of the amount retained in the next assessment.
Often we have remaining activities which need to be undertaken before we achieve Completion. We are of the opinion that these remaining activities should not impact the release of the first half of retention, as the asset is being used for its primary function.
Is there any guidance on the definition of take over or does this need to be something which is agreed between the parties?
Many thanks.