Multiple Notifications: Where a project is made up of multiple sites, it may be impractical to make multiple notifications (F10s). In cases where the work is relatively minor at each location, it may be more appropriate to notify on one form and provide a list of the addresses on the form where there is provision for a description of the construction work involved. This is a free text field in which you can provide more details. For example, if you have indicated on the first page that the work will be undertaken at multiple sites, then a list of those sites can be provided in this field.